Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
Discussion:
32 comments Page 2 of 4.
Aliraza said:
6 years ago
Thanks for all.
Binay said:
8 years ago
I believe beam soffit means the cantilever portion of the beam. It is just a hunch, please correct me if I am wrong.
Malladi said:
6 years ago
What is beam soffit?
Ravi Kumar Maddheshiya said:
8 years ago
Can you explain soffit beam?
Karmveer kohli said:
8 years ago
If all of is not in option then which is right answer?
Sachin Kadam said:
8 years ago
Only 1 day required for vertical members.
Tadesse said:
8 years ago
Vertical form work of column be removed within 16-24 hours.
Younas ahmad said:
1 decade ago
14 days for bottom slabs of spans 4.6 and more.
Chinny said:
8 years ago
What is meant by beam soffit?
Engg chanchal said:
9 years ago
Beam slab and column casting in 20-24 hours remove at form work.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers