Discussion Forum : Concrete Technology - Section 4 (Q.No. 22)
22.
If the effective plan area of a warehouse is 54 sq. m, and maximum height of piles permitted is 270 cm, the number of cement bags to be stored, is
2000 bags
2200 bags
2400 bags
2700 bags
3000 bags
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
21 comments Page 1 of 3.

Denda said:   2 months ago
The weight of 1 kg of cement is 50 kg.
50×57 = 2700.

Wazeer Baloch said:   1 year ago
Area = 54m^2.
height = 270cm = 2.7m,
volume = 54 * 2.7 = 145.8m^3
The Area required for one bag of cement = 0.3m^2,
The height required for one bag of cement = 0.18m.
The volume required for one bag of cement = 0.3 * 0.18 = 0.054m^3.
So, no.of bags = 145.8/0.054 = 2700.
(2)

Jahangir Abbas Sahil said:   4 years ago
The total volume of room = 54 * 2.7 = 145.8 cu.m.
The volume of 1 cement bag = 0.0347 (This is the wet Volume and We've to calculate at site in dry Volume).
Dry Volume= Wet Vol * 1.54 to 1.57,
Dry Volume= 0.0347 * 1.5,
Dry Vol= 0.053 cu.m.

The Number of cement bags = 145.5cum/0.053 = 2745.
Hence, 2745 is near to 2700.
(14)

Sk pratap said:   5 years ago
As per rule the distance between two piles is 1.6m and distance from wall is 30cm and 20cm above the ground level is not included in this calculation why?

According to rule, it is a bad way to store cement in ware house.
(2)

Longti said:   5 years ago
270cm = 2.7m.
(1)

Chandan Nandi said:   5 years ago
2.7 How come?

Please explain.

Er. Anshu kumar said:   5 years ago
Here,

In first case: (standard):

Area required for 1 bag of cement = 0.3 sq.m,
Height of pile required for 1 bag = 0.18 m,
Volume of 1 bag = 0.3 * 0.18,
= 0.054 cubic metre.

In second case:(Given):
Plan area of warehouse = 54 sq.m,
Max.height of piles = 270 cm =2.7 m,
Volume of warehouse = 54*2.7.
= 145.8 cubic metre.

We know that;
No.of bags = volume of warehouse/volume of 1 bag of cement.
= 145.8/0.054.
= 2700 bags.(Answer).
(9)

Beewaek Mandal said:   6 years ago
Simply,

No. Of bags = Effective area* Max.ht of piles/ Area coverd by one bag cement is 0.3 sq.m & ht= 0.18.

No= 54*2.7/0.3*0.18 = 2700 bags you must get.
(3)

Yash said:   6 years ago
When you take 1 bag of cement and plan on group its cover 3000 sq cm area.
And bag height is 18 cm.
That by they use .3 Sqm and .18m here For a bag.

Rahul swarnkar said:   6 years ago
54*2.7/.18*.3 = 2700 bags.