The percentage of the aggregate of F.M. 2.6 to be combined with coarse aggregate of F.M. 6.8 for obtaining the aggregates of F.M. 5.4, is
Discussion:
23 comments Page 3 of 3.
NABIN CHANDRA DAS FROM GIMT said:
10 years ago
{(6.8-5.4)/(5.4-2.6)}*100 = 50%
x = 6.8, y = 2.6, z = 5.4.
C is correct answer.
x = 6.8, y = 2.6, z = 5.4.
C is correct answer.
Rajesh said:
10 years ago
Fineness Modulus-FM.
Agar said:
10 years ago
FM mean?