Discussion Forum : Building Construction - Section 4 (Q.No. 4)
4.
The form work from the slabs excluding props, can be removed only after
1 day
4 days
7 days
14 days
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
17 comments Page 2 of 2.

Ashish Tadewar said:   8 years ago
4 days? How? Can anyone explain it clearly?

Honey said:   9 years ago
It's correct soffit formwork of slab can be removed after 3 days props should be refixed. Since 3 days is not in the option that's why 4 days is correct.

Maari said:   9 years ago
@All.

I think, it is minimum no of days in the question. So the given answer is correct.

Krishan murari roy said:   10 years ago
Shuttering removing after 7 days under 4.5 meter in span.

Mohamed moawad said:   10 years ago
I think for normal strength concrete at 10 days. For rapid strength concrete may be at 4 days.

Vinod kumar kesari said:   1 decade ago
Dear Sir,

I am bit confused at which concept you have to take deshuttering made for slab within 4 days. Setting of concreting depend on environmental condition, span and thickness. But how it would be for 4 days only please explain.

Rajiv sinhmar said:   1 decade ago
My name is Rajiv sinhmar, a civil engg.

I think :- deshuttering mainly depend in two ways 1. Height of span 2. Climate condition (if we are cast the slab in summer season so that early deshutterig but if winter so that time period will be change). So that please suggest me in why take a decision for deshuttering in 4 days.