Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 28)
28.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer: Option
Explanation:
Work done by X in 8 days = | 1 | x 8 | = | 1 | . | ||
40 | 5 |
Remaining work = | 1 - | 1 | = | 4 | . | ||
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | 16 x | 5 | = 20 days. | ||
4 |
X's 1 day's work = | 1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | 1 | + | 1 | = | 3 | . | ||
40 | 20 | 40 |
Hence, X and Y will together complete the work in | 40 | = 13 | 1 | days. | ||
3 | 3 |
Discussion:
32 comments Page 1 of 4.
Shushma Gulla said:
2 months ago
@All.
X - 40
X finished it in 8 days then 40 ÷ 8 = 5.
The efficiency of X is 1/5.
Total efficiency is 1, then Y = 1 - 1/5 = 4/5.
Y finished work in 16 days;
Y days efficiency is 5/4 (reciprocal of Y work efficiency).
Then Y =5/4×16 = 20.
X = 40, Y = 20.
Lcm is 40 (total work)
X is 1 unit, Y is 2 units
Together completed work X, Y is 40/3 = 13(1/3).
X - 40
X finished it in 8 days then 40 ÷ 8 = 5.
The efficiency of X is 1/5.
Total efficiency is 1, then Y = 1 - 1/5 = 4/5.
Y finished work in 16 days;
Y days efficiency is 5/4 (reciprocal of Y work efficiency).
Then Y =5/4×16 = 20.
X = 40, Y = 20.
Lcm is 40 (total work)
X is 1 unit, Y is 2 units
Together completed work X, Y is 40/3 = 13(1/3).
Anonymous said:
3 years ago
@All.
For those who are asking why 5/4 is multiplied,
Let's take an example, Suppose You complete work 1/2 of a work in 2 days. In how much time will you complete the entire work. 4 days right, how did you get it? you multiplied 2.
Eg:
1/2 : 2 is as 1: x, (I took 1 as it is the complete work).
Solving that, you still will get 4 as the answer. Same logic you can apply.
Thank you.
For those who are asking why 5/4 is multiplied,
Let's take an example, Suppose You complete work 1/2 of a work in 2 days. In how much time will you complete the entire work. 4 days right, how did you get it? you multiplied 2.
Eg:
1/2 : 2 is as 1: x, (I took 1 as it is the complete work).
Solving that, you still will get 4 as the answer. Same logic you can apply.
Thank you.
(3)
Ria Sharma said:
3 years ago
Thank you @Mohit.
Thiru said:
4 years ago
Take X's work as 1/40 he can do the work in only 8 days so 1/40*8=1/5.
Now 4/5 part of the work is remaining so Y is completing 4/5 part in 16 days 4/5 * 16 = 1/20.
Asking whole men's work1/20+1/40 = 13 1/3 days.
Now 4/5 part of the work is remaining so Y is completing 4/5 part in 16 days 4/5 * 16 = 1/20.
Asking whole men's work1/20+1/40 = 13 1/3 days.
Yeezuu said:
4 years ago
I am not getting the answer, Can anybody help? please.
(2)
Biswajit das said:
5 years ago
x in 40 days =100% work done.
Then in 08 days= 20 % work done.
The remaining work is 80 % which is done by Y in 16 Days.
in 16 Days =80 % work done.
Then in 20 Days =100 work done.
x=40.
y=20.
LCM =40 (Total work).
X one day work is 01 and 02 is Y's.
Then work done both x and y in= 40/3=13+1/3 Days.
Then in 08 days= 20 % work done.
The remaining work is 80 % which is done by Y in 16 Days.
in 16 Days =80 % work done.
Then in 20 Days =100 work done.
x=40.
y=20.
LCM =40 (Total work).
X one day work is 01 and 02 is Y's.
Then work done both x and y in= 40/3=13+1/3 Days.
(8)
Mir Adil said:
5 years ago
If x does a work at 8 days out of 40 days remaining 32 days are left.
Then y does remaining 32 days work in 16 days itself so Their ratio is 1:2 totally they can do 3 parts in one day, So 3+3+3+3+3+3+3+3+3+3+3+3+3 it completes 39 days here and 1/2 to complete 40 days.
Then y does remaining 32 days work in 16 days itself so Their ratio is 1:2 totally they can do 3 parts in one day, So 3+3+3+3+3+3+3+3+3+3+3+3+3 it completes 39 days here and 1/2 to complete 40 days.
(1)
Ganesh kumar said:
5 years ago
How 4/5 becomes into 5/4?
Please clarify it.
Please clarify it.
Midhun said:
6 years ago
Thanks @Manu.
(1)
Atul said:
6 years ago
Wonderful explanation, thanks @Mohit.
(1)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers