Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 28)
28.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer: Option
Explanation:
Work done by X in 8 days = | ![]() |
1 | x 8 | ![]() |
= | 1 | . |
40 | 5 |
Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 4 | . |
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | ![]() |
16 x | 5 | ![]() |
= 20 days. |
4 |
![]() |
1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 3 | . |
40 | 20 | 40 |
Hence, X and Y will together complete the work in | ![]() |
40 | ![]() |
= 13 | 1 | days. |
3 | 3 |
Discussion:
33 comments Page 1 of 4.
Biswajit das said:
5 years ago
x in 40 days =100% work done.
Then in 08 days= 20 % work done.
The remaining work is 80 % which is done by Y in 16 Days.
in 16 Days =80 % work done.
Then in 20 Days =100 work done.
x=40.
y=20.
LCM =40 (Total work).
X one day work is 01 and 02 is Y's.
Then work done both x and y in= 40/3=13+1/3 Days.
Then in 08 days= 20 % work done.
The remaining work is 80 % which is done by Y in 16 Days.
in 16 Days =80 % work done.
Then in 20 Days =100 work done.
x=40.
y=20.
LCM =40 (Total work).
X one day work is 01 and 02 is Y's.
Then work done both x and y in= 40/3=13+1/3 Days.
(9)
Mohit said:
9 years ago
First LCM of 40 is 40,
x can work 40 days,
work = 1 unit,
8*1 = 8,
remaining work 40 - 8 = 32,
Y finished it in 16 days then = 32/16 = 2,
x+y = 1+2 = 3,
40/3 answer.
x can work 40 days,
work = 1 unit,
8*1 = 8,
remaining work 40 - 8 = 32,
Y finished it in 16 days then = 32/16 = 2,
x+y = 1+2 = 3,
40/3 answer.
(7)
Anonymous said:
4 years ago
@All.
For those who are asking why 5/4 is multiplied,
Let's take an example, Suppose You complete work 1/2 of a work in 2 days. In how much time will you complete the entire work. 4 days right, how did you get it? you multiplied 2.
Eg:
1/2 : 2 is as 1: x, (I took 1 as it is the complete work).
Solving that, you still will get 4 as the answer. Same logic you can apply.
Thank you.
For those who are asking why 5/4 is multiplied,
Let's take an example, Suppose You complete work 1/2 of a work in 2 days. In how much time will you complete the entire work. 4 days right, how did you get it? you multiplied 2.
Eg:
1/2 : 2 is as 1: x, (I took 1 as it is the complete work).
Solving that, you still will get 4 as the answer. Same logic you can apply.
Thank you.
(4)
Yeezuu said:
5 years ago
I am not getting the answer, Can anybody help? please.
(3)
Mir Adil said:
6 years ago
If x does a work at 8 days out of 40 days remaining 32 days are left.
Then y does remaining 32 days work in 16 days itself so Their ratio is 1:2 totally they can do 3 parts in one day, So 3+3+3+3+3+3+3+3+3+3+3+3+3 it completes 39 days here and 1/2 to complete 40 days.
Then y does remaining 32 days work in 16 days itself so Their ratio is 1:2 totally they can do 3 parts in one day, So 3+3+3+3+3+3+3+3+3+3+3+3+3 it completes 39 days here and 1/2 to complete 40 days.
(2)
Manu said:
8 years ago
The total work has done in two parts.
Y completed only 4/5 part of work. another part is done by X.
So work done by Y one day is 1/total work
= 5/4.
But, no need to get confused. simply solve as;
Y completed 4/5 part of work in 16 days.
one day's work is work/days.
divide 4/5 by 16.
We get the answer 1/20 directly.
Y completed only 4/5 part of work. another part is done by X.
So work done by Y one day is 1/total work
= 5/4.
But, no need to get confused. simply solve as;
Y completed 4/5 part of work in 16 days.
one day's work is work/days.
divide 4/5 by 16.
We get the answer 1/20 directly.
(2)
Thiru said:
5 years ago
Take X's work as 1/40 he can do the work in only 8 days so 1/40*8=1/5.
Now 4/5 part of the work is remaining so Y is completing 4/5 part in 16 days 4/5 * 16 = 1/20.
Asking whole men's work1/20+1/40 = 13 1/3 days.
Now 4/5 part of the work is remaining so Y is completing 4/5 part in 16 days 4/5 * 16 = 1/20.
Asking whole men's work1/20+1/40 = 13 1/3 days.
(1)
Ganesh kumar said:
6 years ago
How 4/5 becomes into 5/4?
Please clarify it.
Please clarify it.
(1)
Atul said:
6 years ago
Wonderful explanation, thanks @Mohit.
(1)
Midhun said:
6 years ago
Thanks @Manu.
(1)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers