Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 28)
28.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer: Option
Explanation:
Work done by X in 8 days = | ![]() |
1 | x 8 | ![]() |
= | 1 | . |
40 | 5 |
Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 4 | . |
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | ![]() |
16 x | 5 | ![]() |
= 20 days. |
4 |
![]() |
1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 3 | . |
40 | 20 | 40 |
Hence, X and Y will together complete the work in | ![]() |
40 | ![]() |
= 13 | 1 | days. |
3 | 3 |
Discussion:
32 comments Page 2 of 4.
Sutha said:
6 years ago
How 4/5 becomes into 5/4. Please clarify it.
Prashant singh said:
6 years ago
How 3/40 is converted to 40/3?
Ashis said:
7 years ago
Thanks for the solution @Mohit.
Manu said:
8 years ago
The total work has done in two parts.
Y completed only 4/5 part of work. another part is done by X.
So work done by Y one day is 1/total work
= 5/4.
But, no need to get confused. simply solve as;
Y completed 4/5 part of work in 16 days.
one day's work is work/days.
divide 4/5 by 16.
We get the answer 1/20 directly.
Y completed only 4/5 part of work. another part is done by X.
So work done by Y one day is 1/total work
= 5/4.
But, no need to get confused. simply solve as;
Y completed 4/5 part of work in 16 days.
one day's work is work/days.
divide 4/5 by 16.
We get the answer 1/20 directly.
(2)
Mohit said:
8 years ago
First LCM of 40 is 40,
x can work 40 days,
work = 1 unit,
8*1 = 8,
remaining work 40 - 8 = 32,
Y finished it in 16 days then = 32/16 = 2,
x+y = 1+2 = 3,
40/3 answer.
x can work 40 days,
work = 1 unit,
8*1 = 8,
remaining work 40 - 8 = 32,
Y finished it in 16 days then = 32/16 = 2,
x+y = 1+2 = 3,
40/3 answer.
(5)
Pooka said:
8 years ago
Thank you @Parthasarathy.
P.muthukumar said:
8 years ago
What is the reason for converting 4/5 to 5/4?
Gobind Mandal said:
9 years ago
Why did you convert 4/5 to 5/4?
Makvana Disha said:
9 years ago
We are also do this,
x = 40days = 100%
For 8 days = ? (20%) so, 80% works remaining. That is done by y in 16 days.
80% = 16days
100% = ? (20days)
(x + y)'s 1 day work = (1/40) + (1/20).
= (3/40).
= (40/3) = 13*1/3.
x = 40days = 100%
For 8 days = ? (20%) so, 80% works remaining. That is done by y in 16 days.
80% = 16days
100% = ? (20days)
(x + y)'s 1 day work = (1/40) + (1/20).
= (3/40).
= (40/3) = 13*1/3.
Chetan said:
9 years ago
I am not sure about this answer but changing 4/5 to 5/4 could be because we are finding complete work for Y.
In other problems where same fractions were calculated, there we were finding remaining work. Here for Y, we are finding the Whole work. This could be the reason though I am not sure.
In other problems where same fractions were calculated, there we were finding remaining work. Here for Y, we are finding the Whole work. This could be the reason though I am not sure.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers