Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 23)
23.
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
Answer: Option
Explanation:
2(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 15 | = | 1 | . |
30 | 24 | 20 | 120 | 8 |
Therefore, (A + B + C)'s 1 day's work = | 1 | = | 1 | . |
2 x 8 | 16 |
Work done by A, B, C in 10 days = | 10 | = | 5 | . |
16 | 8 |
Remaining work = | ![]() |
1 - | 5 | ![]() |
= | 3 | . |
8 | 8 |
A's 1 day's work = | ![]() |
1 | - | 1 | ![]() |
= | 1 | . |
16 | 24 | 48 |
Now, | 1 | work is done by A in 1 day. |
48 |
So, | 3 | work will be done by A in | ![]() |
48 x | 3 | ![]() |
= 18 days. |
8 | 8 |
Discussion:
61 comments Page 1 of 7.
S. Kalyan said:
5 years ago
A+B ----> (5/30),
B+C ----> (5/24),
C+A ----> (5/20).
Numerator (A+B+C) worked together for 10 days that means ' A ' Worked 5 days with ' B ' and 5 days with C . Similarly ' B ' Worked 5 days with ' A ' and 5 days with C. And Similarly ' C ' Worked 5 days with ' A ' and 5 days with B.
Now Denominator is their 1-day work :
(5/30) + (5/24) + (5/20) + A * (x) = 1.
Here ' A* (x) ' Means A Completed the Remaining Work (Given in Question) but We Don't Know How many days he Completed the work that is why I have taken (x). Here Represents the days ' A ' Has Worked to Complete that Job.
Now Equation Becomes :
(1/6) + (5/24) + (1/4) + (x * A) = 1.
(5/8) + (x * A) = 1 = > x * A = 1 - (5/8).
=> x * A = (3/8).
To Find ' A's ' 1 Day Work = Total Work Done By all of them - ( Eliminate 2 Variables to Get Value ) (i.e B and C )
So Equation Become,
A's 1 Day Work = (A + B + C)'s 1 day's work - (B + C)'s 1 day's work.
A's 1 Day Work = (1/16) - (1/24) = (1/48).
Now we Got A's 1 Day Work Substitute Above i.e in (x * A).
=> (x/ 48) = (3/8).
Cross Multiplying we get;
=> 8x = 48 * 3.
=> x = 18 days.
Hope You Understood.
B+C ----> (5/24),
C+A ----> (5/20).
Numerator (A+B+C) worked together for 10 days that means ' A ' Worked 5 days with ' B ' and 5 days with C . Similarly ' B ' Worked 5 days with ' A ' and 5 days with C. And Similarly ' C ' Worked 5 days with ' A ' and 5 days with B.
Now Denominator is their 1-day work :
(5/30) + (5/24) + (5/20) + A * (x) = 1.
Here ' A* (x) ' Means A Completed the Remaining Work (Given in Question) but We Don't Know How many days he Completed the work that is why I have taken (x). Here Represents the days ' A ' Has Worked to Complete that Job.
Now Equation Becomes :
(1/6) + (5/24) + (1/4) + (x * A) = 1.
(5/8) + (x * A) = 1 = > x * A = 1 - (5/8).
=> x * A = (3/8).
To Find ' A's ' 1 Day Work = Total Work Done By all of them - ( Eliminate 2 Variables to Get Value ) (i.e B and C )
So Equation Become,
A's 1 Day Work = (A + B + C)'s 1 day's work - (B + C)'s 1 day's work.
A's 1 Day Work = (1/16) - (1/24) = (1/48).
Now we Got A's 1 Day Work Substitute Above i.e in (x * A).
=> (x/ 48) = (3/8).
Cross Multiplying we get;
=> 8x = 48 * 3.
=> x = 18 days.
Hope You Understood.
(2)
Naveen kumar said:
1 decade ago
Hi friends, let me explain one simple method to solve this problem.
It is lengthy process, but you will understand easily.
(a+b)'s 1 day work = 1/30.
(b+c)'s 1 day work = 1/24
(c+a)'s 1 day work = 1/20.
solving that equations we will get
a =1/48 , b = 7/240 , c = 1/80
now,
(a+b+c)'s one day work = 1/48 + 7/240 + 1/80.
= 15/240.
= 1/16.
i.e,
(a+b+c)'s 10 days work = 10/16
=5/8
remaining work = (1- 5/8)
= 3/8
3/8 portion of work is completed by a alone....
now,
a completes 1/48 portion of work in 1 day....
a completes 3/8 portion of work in _ days.....?
1/48------> 1
3/8-------> x
by cross multyplying,we will get
x /48 = 3/8
x = 18..
So, A alone can complete the work in 18 days.
It is lengthy process, but you will understand easily.
(a+b)'s 1 day work = 1/30.
(b+c)'s 1 day work = 1/24
(c+a)'s 1 day work = 1/20.
solving that equations we will get
a =1/48 , b = 7/240 , c = 1/80
now,
(a+b+c)'s one day work = 1/48 + 7/240 + 1/80.
= 15/240.
= 1/16.
i.e,
(a+b+c)'s 10 days work = 10/16
=5/8
remaining work = (1- 5/8)
= 3/8
3/8 portion of work is completed by a alone....
now,
a completes 1/48 portion of work in 1 day....
a completes 3/8 portion of work in _ days.....?
1/48------> 1
3/8-------> x
by cross multyplying,we will get
x /48 = 3/8
x = 18..
So, A alone can complete the work in 18 days.
Nikhil said:
1 decade ago
A+B = 30 days.
B+C = 24 days.
C+A = 20 days.
--------------------
divide by taking lcm (30,24,20) = 120.
A+B = 4 units.
B+C = 5 units.
C+A = 6 units.
-------------------
2( A+B+C) = 15 units.
A+B+C =7.5 units.
They work together 10 days, means in 10 days they have completed 75 units out of 120 units. now,
Remaining units are (120-75) = 45.
A+B+C = 7.5 (put B+C= 5 as given),
A = 2.5.
So for completing 45 units, A need (45/2.5) = 18 days.
B+C = 24 days.
C+A = 20 days.
--------------------
divide by taking lcm (30,24,20) = 120.
A+B = 4 units.
B+C = 5 units.
C+A = 6 units.
-------------------
2( A+B+C) = 15 units.
A+B+C =7.5 units.
They work together 10 days, means in 10 days they have completed 75 units out of 120 units. now,
Remaining units are (120-75) = 45.
A+B+C = 7.5 (put B+C= 5 as given),
A = 2.5.
So for completing 45 units, A need (45/2.5) = 18 days.
(18)
Vinoth said:
9 years ago
From the very first statement, we can calculate,
A's one day work as 1/60 i.e. (1/30) *(1/2). But they have done some confused calculations and saying that A's 1-day work is 1/48 this is not possible.
The ANSWER IS 22 + 1/2 days.
You all just check it by putting (10days A + B + C work ) + (22 + 1/2 days A's work alone) = 1. Then, you will get 1 which is the total work done
A's one day work as 1/60 i.e. (1/30) *(1/2). But they have done some confused calculations and saying that A's 1-day work is 1/48 this is not possible.
The ANSWER IS 22 + 1/2 days.
You all just check it by putting (10days A + B + C work ) + (22 + 1/2 days A's work alone) = 1. Then, you will get 1 which is the total work done
Bikash Choudhury said:
1 decade ago
LCM of 30, 24, 20 is 120.
A+B B+C C+A A+B+C.
4 5 6 2 (a+b+c) = 15.
=> a+b+c = 15/2.
A+B+C do for 10 means they work together 10*15/2 = 75 units of work.
Work remains 120-75 = 45 unit.
A 's one day work = (A+B+C)-(B+C) = 15/2-5 = 5/2.
Hence A can finish the remaining work = 45*2/5 = 18.
A+B B+C C+A A+B+C.
4 5 6 2 (a+b+c) = 15.
=> a+b+c = 15/2.
A+B+C do for 10 means they work together 10*15/2 = 75 units of work.
Work remains 120-75 = 45 unit.
A 's one day work = (A+B+C)-(B+C) = 15/2-5 = 5/2.
Hence A can finish the remaining work = 45*2/5 = 18.
(3)
Mithun said:
8 years ago
GIVEN: A+B B+C A+C.
FORMULA: 2(A+B+C) = (A+B)(B+C)(A+C)
=2(1/8)
=1/16
GET A:
A+B+C=1/16, B+C=1/24.
(A+B+C) - (B+C) =1/16-1/24.
By solving we get A as 1/48.
10/16 + x/48=1 [ABC worked for 10days]
x=18.
FORMULA: 2(A+B+C) = (A+B)(B+C)(A+C)
=2(1/8)
=1/16
GET A:
A+B+C=1/16, B+C=1/24.
(A+B+C) - (B+C) =1/16-1/24.
By solving we get A as 1/48.
10/16 + x/48=1 [ABC worked for 10days]
x=18.
Srk S said:
5 years ago
@Tanvir,
A's one-day work = Total 1-day work of (A+B+C) - One day work of (B+C)
Total 1-day work of (A+B+C) is found by us while solving.
One day work of (B+C) is given in the question.
Therefore,
A's one-day work = (1/16) - (1/24).
A's one-day work = 1/48.
A's one-day work = Total 1-day work of (A+B+C) - One day work of (B+C)
Total 1-day work of (A+B+C) is found by us while solving.
One day work of (B+C) is given in the question.
Therefore,
A's one-day work = (1/16) - (1/24).
A's one-day work = 1/48.
Sudarshan yadav said:
1 decade ago
2(a+b+c) 1 days work =1/8 then a+b+c 1 day work=1/16 then a's 1 day work=1/16-1/24=1/48 then in 10 days a+b+c can do 10/16 work now remaining work=1-10/16=3/8 now in 48 days a can do 1 work then 3/8 work a can do in 48*3/8=18.
Manu said:
1 decade ago
Nice work guys. I really didn't understand how we calculated A's one days work 1/48 but after reading discussions I got the answer, nice work by all of you.
Surya said:
1 decade ago
A+B=1/30 AND B+C=1/24 AND C+A=1/20.
As per question all work together means : a+b+b+c+c+a=2a+2b+2c;
2 is common factor so we can write it as 2(a+b+c).
As per question all work together means : a+b+b+c+c+a=2a+2b+2c;
2 is common factor so we can write it as 2(a+b+c).
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers