Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 23)
23.
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
18 days
24 days
30 days
36 days
Answer: Option
Explanation:

2(A + B + C)'s 1 day's work = ( 1 + 1 + 1 ) = 15 = 1 .
30 24 20 120 8

Therefore, (A + B + C)'s 1 day's work = 1 = 1 .
2 x 8 16

Work done by A, B, C in 10 days = 10 = 5 .
16 8

Remaining work = ( 1 - 5 ) = 3 .
8 8

A's 1 day's work = ( 1 - 1 ) = 1 .
16 24 48

Now, 1 work is done by A in 1 day.
48

So, 3 work will be done by A in ( 48 x 3 ) = 18 days.
8 8

Discussion:
61 comments Page 1 of 7.

Vikas kumar said:   3 years ago
LCM = 120.

A=2.5,
B=3.5,
C=1.5.

A + B + C = 7.5 for 10days all works togather then 7.5*10=75,
Remaining=120 - 75 = 45.
For A = 45/2.5 = 18days.
(18)

Nikhil said:   1 decade ago
A+B = 30 days.
B+C = 24 days.
C+A = 20 days.
--------------------

divide by taking lcm (30,24,20) = 120.
A+B = 4 units.
B+C = 5 units.
C+A = 6 units.
-------------------

2( A+B+C) = 15 units.
A+B+C =7.5 units.

They work together 10 days, means in 10 days they have completed 75 units out of 120 units. now,

Remaining units are (120-75) = 45.

A+B+C = 7.5 (put B+C= 5 as given),

A = 2.5.

So for completing 45 units, A need (45/2.5) = 18 days.
(18)

KEYA said:   4 years ago
(A+B+C) = 1/16.
(B+C) = 1/24.

Hence,
A = 1/16 - 1/24 = 1/48.
(16)

Subash said:   7 years ago
By approx too we can solve this;

a+b+c=1/10,
b+c=1/24,
a=1/10-1/24,
a=17.13,
Near by value 18.
(5)

Bikash Choudhury said:   1 decade ago
LCM of 30, 24, 20 is 120.

A+B B+C C+A A+B+C.

4 5 6 2 (a+b+c) = 15.

=> a+b+c = 15/2.

A+B+C do for 10 means they work together 10*15/2 = 75 units of work.

Work remains 120-75 = 45 unit.

A 's one day work = (A+B+C)-(B+C) = 15/2-5 = 5/2.

Hence A can finish the remaining work = 45*2/5 = 18.
(3)

S. Kalyan said:   5 years ago
A+B ----> (5/30),

B+C ----> (5/24),

C+A ----> (5/20).


Numerator (A+B+C) worked together for 10 days that means ' A ' Worked 5 days with ' B ' and 5 days with C . Similarly ' B ' Worked 5 days with ' A ' and 5 days with C. And Similarly ' C ' Worked 5 days with ' A ' and 5 days with B.

Now Denominator is their 1-day work :

(5/30) + (5/24) + (5/20) + A * (x) = 1.

Here ' A* (x) ' Means A Completed the Remaining Work (Given in Question) but We Don't Know How many days he Completed the work that is why I have taken (x). Here Represents the days ' A ' Has Worked to Complete that Job.

Now Equation Becomes :
(1/6) + (5/24) + (1/4) + (x * A) = 1.

(5/8) + (x * A) = 1 = > x * A = 1 - (5/8).

=> x * A = (3/8).

To Find ' A's ' 1 Day Work = Total Work Done By all of them - ( Eliminate 2 Variables to Get Value ) (i.e B and C )

So Equation Become,
A's 1 Day Work = (A + B + C)'s 1 day's work - (B + C)'s 1 day's work.
A's 1 Day Work = (1/16) - (1/24) = (1/48).

Now we Got A's 1 Day Work Substitute Above i.e in (x * A).

=> (x/ 48) = (3/8).

Cross Multiplying we get;

=> 8x = 48 * 3.
=> x = 18 days.

Hope You Understood.
(2)

Vinod said:   7 years ago
Thank you @Nihkil.
(2)

Anandhi said:   1 decade ago
A+B+C one day work = 1/16.
Given B+C = 1/24.

Therefore A+B+C = 1/16.
A+1/24 = 1/16.
A = 1/16-1/24.

A = 1/48.
(2)

Nandhakumar said:   1 decade ago
how to find A's 1's day work
(1)

Sikandar said:   1 decade ago
As 1 day work = (A+B+C)-(B+C).

= 1/16-1/24 = 1/48.
(1)


Post your comments here:

Your comments will be displayed after verification.