Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 10)
10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
Answer: Option
Explanation:
(P + Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 37 | . |
8 | 10 | 12 | 120 |
Work done by P, Q and R in 2 hours = | ![]() |
37 | x 2 | ![]() |
= | 37 | . |
120 | 60 |
Remaining work = | ![]() |
1 - | 37 | ![]() |
= | 23 | . |
60 | 60 |
(Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 11 | . |
10 | 12 | 60 |
Now, | 11 | work is done by Q and R in 1 hour. |
60 |
So, | 23 | work will be done by Q and R in | ![]() |
60 | x | 23 | ![]() |
= | 23 | hours ![]() |
60 | 11 | 60 | 11 |
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
Discussion:
95 comments Page 1 of 10.
Dhinesh said:
1 year ago
P = 1/8 the amount of work in one day.
Q = 1/10 amount of work in one day.
R = 1/12 amount of work in one day.
All machines start at 9.00 AM.
Machine P stopped at 11.00 AM so it worked 2hrs,
11.00AM - 9.00AM = 2hrs.
P's work in 2hrs = 2(1/8) = 1/4.
Remaining work = 1 - (1/4) = 3/4 pending.
Q+R 's work in one day=(1/10)+(1/12)=11/60
to complete 3/4 of the work, Q and R need 'x' Days.
x(11/60) = 3/4
x = (3/4) * (60/11),
x = 45/11,
x = 4.99 (approx. 5hrs)
5 hours from 9AM is 1.00 PM
Q = 1/10 amount of work in one day.
R = 1/12 amount of work in one day.
All machines start at 9.00 AM.
Machine P stopped at 11.00 AM so it worked 2hrs,
11.00AM - 9.00AM = 2hrs.
P's work in 2hrs = 2(1/8) = 1/4.
Remaining work = 1 - (1/4) = 3/4 pending.
Q+R 's work in one day=(1/10)+(1/12)=11/60
to complete 3/4 of the work, Q and R need 'x' Days.
x(11/60) = 3/4
x = (3/4) * (60/11),
x = 45/11,
x = 4.99 (approx. 5hrs)
5 hours from 9AM is 1.00 PM
(39)
Sai Vinitha said:
3 years ago
P - 8 d
Q - 10 d
R - 12 d -------now,LCM of p,q,r is 120.
So, P's one day hour work = 15.
Q's =12
R's. =10.
P works for 2 hours.
So, 2*15=30.
120-30=90.
Remaining work is done by Q and R = 90/22 = 4(approx).
9:00 AM + 4 hrs = 1:00 PM.
Q - 10 d
R - 12 d -------now,LCM of p,q,r is 120.
So, P's one day hour work = 15.
Q's =12
R's. =10.
P works for 2 hours.
So, 2*15=30.
120-30=90.
Remaining work is done by Q and R = 90/22 = 4(approx).
9:00 AM + 4 hrs = 1:00 PM.
(37)
Abhishek said:
3 years ago
Ok, since work done is the same for all the machines,( to print 1 lakh papers) you can assume any number to be your work done, cleverly you always assume the LCM of time given.
LCM of 8,10 and 12 is 120).
So let the work is to print 120 papers.
Given;
MACHINE ---- TIME ---- efficiency
P ---- 8 ---- 15
Q ---- 10 ---- 12
R ---- 12 ---- 10.
Now P works for 2 hours, So it will print 30 pages, and the remaining 120-30, 90 pages will be printed by Q and R.
Therefore time taken = 90/22 = 4 hrs approx.
Therefore, the finishing time will be 1 am.
LCM of 8,10 and 12 is 120).
So let the work is to print 120 papers.
Given;
MACHINE ---- TIME ---- efficiency
P ---- 8 ---- 15
Q ---- 10 ---- 12
R ---- 12 ---- 10.
Now P works for 2 hours, So it will print 30 pages, and the remaining 120-30, 90 pages will be printed by Q and R.
Therefore time taken = 90/22 = 4 hrs approx.
Therefore, the finishing time will be 1 am.
(31)
Divya said:
1 year ago
P=80,
Q=10,
R=12.
L.C.M = 120
P=15,Q = 12,R = 10
For 2 hours = 2*15+12+10 = 27units
The remaining 66 units are (Q+R)
Q+R = 12+10 = 22
Q+R = 66/22 = 3hours
11 A.M + 3hours = 1 P.M.
Q=10,
R=12.
L.C.M = 120
P=15,Q = 12,R = 10
For 2 hours = 2*15+12+10 = 27units
The remaining 66 units are (Q+R)
Q+R = 12+10 = 22
Q+R = 66/22 = 3hours
11 A.M + 3hours = 1 P.M.
(22)
Dharmendra pandian S said:
2 years ago
P= 1 lakh = for 1 hr 12500.
Q= 1 lakh = for 1 hr 10000.
R= 1 lakh = for 1 hr 8333.
The three of them did for 9:00 am to 11:00 am so the job done is 61,666 books printed and then;
The balance they are 100000-61666 = 38,334.
So, take q +r = 18333 and try with each multiple which is near to that 38,334
18333×2 = 36,666.
So they take 2 hrs add with 11:00 then;
Answer will be 1:00 pm.
Q= 1 lakh = for 1 hr 10000.
R= 1 lakh = for 1 hr 8333.
The three of them did for 9:00 am to 11:00 am so the job done is 61,666 books printed and then;
The balance they are 100000-61666 = 38,334.
So, take q +r = 18333 and try with each multiple which is near to that 38,334
18333×2 = 36,666.
So they take 2 hrs add with 11:00 then;
Answer will be 1:00 pm.
(21)
Rose said:
2 years ago
Total work=120 units(lim of 8;10;12).
Efficiency of p-15.
“ of Q-12.
“Of R-10.
For 2 hours(9-11)all three worked = 2 *27 = 54units.
The remaining 66 units are covered by Q+R=66/22 = 3hrs.
11 am+3 hrs~ = 1 pm.
Efficiency of p-15.
“ of Q-12.
“Of R-10.
For 2 hours(9-11)all three worked = 2 *27 = 54units.
The remaining 66 units are covered by Q+R=66/22 = 3hrs.
11 am+3 hrs~ = 1 pm.
(18)
Priyadharshini said:
3 years ago
P = 2/8, Q = (2+x)/10, R = (2+x)/12.
(2/8)+(2+x)/10+(2+x)/12 = 1.
By solving this equation we get x = 2 hrs.
so the answer is 1PM (11AM+2hrs).
(2/8)+(2+x)/10+(2+x)/12 = 1.
By solving this equation we get x = 2 hrs.
so the answer is 1PM (11AM+2hrs).
(15)
Preetithapa said:
6 months ago
p-8hr , Q -10hr R - 12 hr.
Total work (LCM) - 120 unit.
Efficiency of P, Q, R - 15, 12, 10 .
For 2hr - 2(15+12+10) = 74 unit.
The remaining work- 46 units.
The time taken by (Q+R) =2.09 hr ~2hr.
9:00am + 2hr = 11 am.
11am + 2hr = 1 pm.
Total work (LCM) - 120 unit.
Efficiency of P, Q, R - 15, 12, 10 .
For 2hr - 2(15+12+10) = 74 unit.
The remaining work- 46 units.
The time taken by (Q+R) =2.09 hr ~2hr.
9:00am + 2hr = 11 am.
11am + 2hr = 1 pm.
(14)
Arundhati Rajpurohit said:
3 years ago
So the easiest way to solve this:
P Q R from 9 am to 11 am do work together so;
For p 1 lakh - 8hrs.
In 2 hrs - 25000 work.
For q 1 lakh- 10hrs.
In 2 hrs - 20000.
For r 1 lakh - 12 hrs.
In 2 hrs- 16666.67.
Total work done in 2 hrs.
25000+20000+16666= 61666.
Remaining work = 38334
So R+Q work from 11 am together,
Q do 10000 in an hr.
R do 8333
Together they do approx 18333 in an hr.
Hence;
In 2 hrs they do 36666 something work which is approximately equals to 38334.
So, they will complete the work around 1 pm.
P Q R from 9 am to 11 am do work together so;
For p 1 lakh - 8hrs.
In 2 hrs - 25000 work.
For q 1 lakh- 10hrs.
In 2 hrs - 20000.
For r 1 lakh - 12 hrs.
In 2 hrs- 16666.67.
Total work done in 2 hrs.
25000+20000+16666= 61666.
Remaining work = 38334
So R+Q work from 11 am together,
Q do 10000 in an hr.
R do 8333
Together they do approx 18333 in an hr.
Hence;
In 2 hrs they do 36666 something work which is approximately equals to 38334.
So, they will complete the work around 1 pm.
(14)
Baji said:
4 years ago
This problem is simple;
First, see the difference between the machine completed work it's approximately 2 hours in each machine.
So, p machine end it's work is 11 am so,
The difference is 2.
So simply add that 11+2= 1 pm.
First, see the difference between the machine completed work it's approximately 2 hours in each machine.
So, p machine end it's work is 11 am so,
The difference is 2.
So simply add that 11+2= 1 pm.
(13)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers