10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
11:30 A.M.
12 noon
12:30 P.M.
1:00 P.M.
Answer: Option
Explanation:

(P + Q + R)'s 1 hour's work = ( 1 + 1 + 1 ) = 37 .
8 10 12 120

Work done by P, Q and R in 2 hours = ( 37 x 2 ) = 37 .
120 60

Remaining work = ( 1 - 37 ) = 23 .
60 60

(Q + R)'s 1 hour's work = ( 1 + 1 ) = 11 .
10 12 60

Now, 11 work is done by Q and R in 1 hour.
60

So, 23 work will be done by Q and R in ( 60 x 23 ) = 23 hours = 2 hours.
60 11 60 11

So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.

Discussion:
95 comments Page 2 of 10.

Joel said:   4 years ago
Take lcm of 8, 10'12.

Lcm = 120 units book to be printed.
P = 120/8 = 15 units/ hour.
Q = 120/10 = 12 units per hour.
R = 120/12 = 10 units per hour.

Total units per hour=15+12+10=37 units per hour.

P+q+r work together for two hour=37*2=74 units for two hours.

Remaining work=120-72=46 units.

P and R one hour efficiency=12+10=22 units per hour.
They need how much time to finish 46 units?

46/22 = 2.09 hours.

After 11 am they need 2 hours means 1 pm approximately.
(8)

Aaren said:   1 year ago
@All.

According to me, the Time taken for P, Q, R machines together to print everything will be 120/37 ~3.5 hours or about 12:30 pm.
So, if one machine stops working in between then obviously it will take more time than 12:30 and there was only one option satisfying this condition.

Anyone, please clarify this to me clearly.
(8)

Harini Murali said:   3 weeks ago
P - 1,00,000 = 8H.
Q - 1,00,000 = 10H.
R - 1,00,000 = 12H.

P, Q, R start at 9.00AM,
P = 11.00AM finished,
R - P = 2H.
Total 2 hrs difference,
11.00AM + 2 = 1:00 PM.
Then Ans : 1.00pm.
(3)

PADAMATA PAVAN KUMAR said:   1 year ago
Total unit of work is 240 units.p done per hour 30 units and q done 24 units and r done 20 units per hour.
Now three worked per 2 hr i.e 2(30×24×20)=148 units, remaining=240-148=92 units.
Now p left so only q and r can do in 1 hr (24+20)=44 units .
If they both worked for 2hr.
i.e 44×2=88 units then the total work will finish here 92approx 88,
So, take 2 hr 11 to 2 hr means 1 P.M.
(3)

Rojash thapa said:   3 years ago
Please somebody help me to solve this problem in an easy way.
(2)

Keval shah said:   1 year ago
Thanks for the explanation @Sai Vinitha.
(2)

Sukanya said:   9 years ago
The difference between every machine is two hours, so 2hr + 11hr = 13 hrs, ie 1:00 clock.
(2)

Parthiban said:   5 years ago
8,10,12 for this lcm 120

Assume 120 books print
Machines printing per hour
P 120/8 = 15
Q 120/10=12
R 120/12=10.

Per hour 3 machine together print books 37

Start 9 am 11 pm machine p stop the work.

2 hours all machine worked so 2 *37=74.

120-74=46 machine Q R together print in one hour 10+12=22.

So 46/22 =2.02 so 2 hours required to print remains books
After 11 am need 2 hours need so answer 1 pm.
(2)

Tanmay chahande said:   5 years ago
See,

P works for 8 hours.
Q works for 10 hours.
R works for 12 hours.

The total time taken by the three machines is 30 hours that is 1 day and 6 hours.

Next condition says that three machines start at 9,00 am and p stops in 2 hours means machines worked for 1 Day and 4 hours now when we calculate 1 day 4 hours from 9.00 am we get clock time 1.00 pm.
(2)

Barshan Roy said:   5 months ago
Well explained. Thanks all.
(1)