Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 10)
10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
11:30 A.M.
12 noon
12:30 P.M.
1:00 P.M.
Answer: Option
Explanation:

(P + Q + R)'s 1 hour's work = ( 1 + 1 + 1 ) = 37 .
8 10 12 120

Work done by P, Q and R in 2 hours = ( 37 x 2 ) = 37 .
120 60

Remaining work = ( 1 - 37 ) = 23 .
60 60

(Q + R)'s 1 hour's work = ( 1 + 1 ) = 11 .
10 12 60

Now, 11 work is done by Q and R in 1 hour.
60

So, 23 work will be done by Q and R in ( 60 x 23 ) = 23 hours = 2 hours.
60 11 60 11

So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.

Discussion:
95 comments Page 1 of 10.

Harini Murali said:   3 weeks ago
P - 1,00,000 = 8H.
Q - 1,00,000 = 10H.
R - 1,00,000 = 12H.

P, Q, R start at 9.00AM,
P = 11.00AM finished,
R - P = 2H.
Total 2 hrs difference,
11.00AM + 2 = 1:00 PM.
Then Ans : 1.00pm.
(3)

Barshan Roy said:   5 months ago
Well explained. Thanks all.
(1)

Preetithapa said:   6 months ago
p-8hr , Q -10hr R - 12 hr.
Total work (LCM) - 120 unit.
Efficiency of P, Q, R - 15, 12, 10 .

For 2hr - 2(15+12+10) = 74 unit.
The remaining work- 46 units.

The time taken by (Q+R) =2.09 hr ~2hr.

9:00am + 2hr = 11 am.
11am + 2hr = 1 pm.
(14)

Dhinesh said:   1 year ago
P = 1/8 the amount of work in one day.
Q = 1/10 amount of work in one day.
R = 1/12 amount of work in one day.

All machines start at 9.00 AM.
Machine P stopped at 11.00 AM so it worked 2hrs,
11.00AM - 9.00AM = 2hrs.

P's work in 2hrs = 2(1/8) = 1/4.
Remaining work = 1 - (1/4) = 3/4 pending.

Q+R 's work in one day=(1/10)+(1/12)=11/60
to complete 3/4 of the work, Q and R need 'x' Days.
x(11/60) = 3/4
x = (3/4) * (60/11),
x = 45/11,
x = 4.99 (approx. 5hrs)

5 hours from 9AM is 1.00 PM
(39)

Aaren said:   1 year ago
@All.

According to me, the Time taken for P, Q, R machines together to print everything will be 120/37 ~3.5 hours or about 12:30 pm.
So, if one machine stops working in between then obviously it will take more time than 12:30 and there was only one option satisfying this condition.

Anyone, please clarify this to me clearly.
(8)

Keval shah said:   1 year ago
Thanks for the explanation @Sai Vinitha.
(2)

PADAMATA PAVAN KUMAR said:   1 year ago
Total unit of work is 240 units.p done per hour 30 units and q done 24 units and r done 20 units per hour.
Now three worked per 2 hr i.e 2(30×24×20)=148 units, remaining=240-148=92 units.
Now p left so only q and r can do in 1 hr (24+20)=44 units .
If they both worked for 2hr.
i.e 44×2=88 units then the total work will finish here 92approx 88,
So, take 2 hr 11 to 2 hr means 1 P.M.
(3)

Divya said:   1 year ago
P=80,
Q=10,
R=12.

L.C.M = 120
P=15,Q = 12,R = 10
For 2 hours = 2*15+12+10 = 27units
The remaining 66 units are (Q+R)
Q+R = 12+10 = 22
Q+R = 66/22 = 3hours
11 A.M + 3hours = 1 P.M.
(22)

Rose said:   2 years ago
Total work=120 units(lim of 8;10;12).

Efficiency of p-15.
“ of Q-12.
“Of R-10.

For 2 hours(9-11)all three worked = 2 *27 = 54units.
The remaining 66 units are covered by Q+R=66/22 = 3hrs.
11 am+3 hrs~ = 1 pm.
(18)

Dharmendra pandian S said:   2 years ago
P= 1 lakh = for 1 hr 12500.
Q= 1 lakh = for 1 hr 10000.
R= 1 lakh = for 1 hr 8333.

The three of them did for 9:00 am to 11:00 am so the job done is 61,666 books printed and then;

The balance they are 100000-61666 = 38,334.
So, take q +r = 18333 and try with each multiple which is near to that 38,334
18333×2 = 36,666.
So they take 2 hrs add with 11:00 then;
Answer will be 1:00 pm.
(21)


Post your comments here:

Your comments will be displayed after verification.