11.
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
5

5 1
2

6
8
Answer: Option
Explanation:

B's 10 day's work = ( 1 x 10 ) = 2 .
15 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 1 day.
18

Therefore 1 work is done by A in ( 18 x 1 ) = 6 days.
3 3

Discussion:
63 comments Page 6 of 7.

Ranjit said:   8 years ago
X/18 +10/15 =1.
X+12 = 18,
X = 18 - 12,
= 6 days.

Raja said:   1 decade ago
LCM 90 brief explain?
Left the job B what mean?

Kamu said:   6 years ago
Can't get it. Please explain me clearly.

Kusum said:   1 decade ago
Can anyone explain this 1/3*18 ? please.

Mehru Qamar said:   4 years ago
Thank you @Shashidhar B Challamarada.
(2)

Sayali said:   1 decade ago
@Rucha.

How you calculate that rate?

Arsh said:   10 years ago
{(1/15)*10}+{(1/18)*x} = 1.

x = 6.

Santhiya' said:   8 years ago
Good explanation. Thank you all.

Gobinath b said:   1 decade ago
Anyone can you how it is?

Sowndarya said:   9 years ago
Simple & super @Arsh.


Post your comments here:

Your comments will be displayed after verification.