Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 11)
11.
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
5

5 1
2

6
8
Answer: Option
Explanation:

B's 10 day's work = ( 1 x 10 ) = 2 .
15 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 1 day.
18

Therefore 1 work is done by A in ( 18 x 1 ) = 6 days.
3 3

Discussion:
63 comments Page 5 of 7.

Willoy said:   1 decade ago
The question is flawed.

Both A and B finish the job in 8 days.

Compute for work done rather than remaining:

A[work per day] = 0.05556.

B[work per day] = 0.06667.

A+B[8 days work] = 0.97784.

A+B[10 days work] = 1.2223 <--- job over done.

B left the job because he's not doing anything anymore.

Anonymous said:   1 decade ago
The question is flawed. Both A and B can do the work together in less than 10 days. Consider revising the wording of the problem.

A[WorkPerDay] = 0.05556.
B[WorkPerDay] = 0.06667.

Cumulatively in 10 days the total is 1.2223, which is more than enough to finish the work.

A and B finish the work in 8 days.

SAGAR said:   1 decade ago
10*1/15+x*1/18 = 1.
By solving you get x = 6 days.

Sayali said:   1 decade ago
@Rucha.

How you calculate that rate?

Deepak Patgar said:   1 decade ago
It will be easy if we use chocolate method.

A takes 18 days and B takes 15 days. LCM of 18 and 15 is 90.
Let 90 be the total number of chocolates.

A takes 18 days to eat 90 chocolates. so A eats 5 chocolates per day.
B takes 15 days to eat 90 chocolates. So B eats 6 chocolates per day.

in 10 days B finishes 6*10 = 60 chocolates.
Remaining chocolates are 30.

So to eat 30 chocolates A need 30/5 = 6 days.
Ans = 6 days.

Raja said:   1 decade ago
LCM 90 brief explain?
Left the job B what mean?

Ajay Singh said:   1 decade ago
See as per my knowledge of solving such question it should be in this way:

A's 1 day work=1/18,
B's 1 day work=1/15,
Both (A+B)'s 1 day work =1/18+1/15=1/10,
So their 10 days of work together will be=1/10*10=1,
Thus,remaining work =1-1=0,

So, in my opinion this question is incorrect.
Please reply if I am wrong and give possible solution.

Ruchi Jain said:   1 decade ago
Well the way I solve this question,
     A   B     B
T 18 15 10
R 5 6 6
W 90 90 60

REMAINING IS 30 which is to be done by A and A's rate is 5 30/5 = 6.

Swapnika said:   1 decade ago
A done in 18 says so we can do in this way also:

18*5 //therefore (15-10=5).
18*5 = 90.
90/15 = 6.

Meher said:   1 decade ago
I don't understand the logic of multiplying 18*1/3.


Post your comments here:

Your comments will be displayed after verification.