Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 4 of 35.
Mish said:
2 years ago
@All.
Why (A+B)'s 4 days of work is calculated?
Why it's not 3,5,6,7 or any other day?
What is the logic behind it?
Why (A+B)'s 4 days of work is calculated?
Why it's not 3,5,6,7 or any other day?
What is the logic behind it?
(10)
Zak said:
2 years ago
How come 7/60? Please explain.
(29)
Dinesh kumar said:
2 years ago
A = 1/15
B = 1/20
(A+B) = 1/15+1/20 = 7/15
The remaining work = 1-7/15 = 8/15.
B = 1/20
(A+B) = 1/15+1/20 = 7/15
The remaining work = 1-7/15 = 8/15.
(26)
Jeevanantham M said:
2 years ago
@Ayansh.
For this;
(A+B) 's work rate = 1/15 + 1/20 = (4/60 + 3/60) = 7/60.
For this;
(A+B) 's work rate = 1/15 + 1/20 = (4/60 + 3/60) = 7/60.
(21)
Sandeep said:
2 years ago
A's 1 day's work = 1/15;
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15+1/20)= 7/60;
Total days required to complete total work of (A+B) = 60/7,
After 4 days, remaining days left = 60/7 - 4 = 32/7,
Hence, remaining work = 32/7 x 7/60 = 8/15,
Hope it helps.
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15+1/20)= 7/60;
Total days required to complete total work of (A+B) = 60/7,
After 4 days, remaining days left = 60/7 - 4 = 32/7,
Hence, remaining work = 32/7 x 7/60 = 8/15,
Hope it helps.
(63)
Vicky Kumar said:
2 years ago
A completed this in 15 days.
Then, A completed this work in 1 days = (1/15).
B completed this work in 20 days
Then, B completed this work in 1 days = (1/20).
Both A and B both completed this work in 1 days = (A+B)
= ((1/15)+(1/20)).
then, the LCM of 15 and 20 is 60;
we get,
((1*4)+(1*3)/60))
= 7/60.
A and B both completed the same work in 4 days = ((7/60)*4)
= 7/15.
Let's take total work is = 1.
then we know that,
Rest work= total work - completed work.
= 1 - (7/15).
= (15-7)/15.
= 8/15 Answer.
Then, A completed this work in 1 days = (1/15).
B completed this work in 20 days
Then, B completed this work in 1 days = (1/20).
Both A and B both completed this work in 1 days = (A+B)
= ((1/15)+(1/20)).
then, the LCM of 15 and 20 is 60;
we get,
((1*4)+(1*3)/60))
= 7/60.
A and B both completed the same work in 4 days = ((7/60)*4)
= 7/15.
Let's take total work is = 1.
then we know that,
Rest work= total work - completed work.
= 1 - (7/15).
= (15-7)/15.
= 8/15 Answer.
(81)
RichardAnthony said:
2 years ago
Just take LCM of 15 and 20 you will get total work of 60.
(17)
Sankalp said:
2 years ago
Please explain, why the remaining work is 1.
(60)
Vinitha said:
2 years ago
@all
(1/15+1/20) =7/60.
Solution:
We have to use the mixed fraction method in a simple way using cross multiplication so it becomes (15+20)/300.
The reason for the 300 came we use the denominator direct multiplication (15*20=300)
Then 15+20 = 35,
Divide:35/300.
It becomes 7/60.
(1/15+1/20) =7/60.
Solution:
We have to use the mixed fraction method in a simple way using cross multiplication so it becomes (15+20)/300.
The reason for the 300 came we use the denominator direct multiplication (15*20=300)
Then 15+20 = 35,
Divide:35/300.
It becomes 7/60.
(38)
Radhika said:
3 years ago
@All.
As 1 is the whole work, so when we subtract 7/15 from 1.
Then,
LCM of 1 and 15 will be 15 ( in 1 the denominator will be 1 ).
So, 15-7/15 is 8/15.
As 1 is the whole work, so when we subtract 7/15 from 1.
Then,
LCM of 1 and 15 will be 15 ( in 1 the denominator will be 1 ).
So, 15-7/15 is 8/15.
(18)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers