1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
347 comments Page 5 of 35.

Sankalp said:   3 years ago
Please explain, why the remaining work is 1.
(60)

Vinitha said:   3 years ago
@all
(1/15+1/20) =7/60.
Solution:
We have to use the mixed fraction method in a simple way using cross multiplication so it becomes (15+20)/300.
The reason for the 300 came we use the denominator direct multiplication (15*20=300)
Then 15+20 = 35,
Divide:35/300.
It becomes 7/60.
(38)

Radhika said:   3 years ago
@All.

As 1 is the whole work, so when we subtract 7/15 from 1.
Then,
LCM of 1 and 15 will be 15 ( in 1 the denominator will be 1 ).
So, 15-7/15 is 8/15.
(18)

Ayansh said:   3 years ago
How (1/15+1/20) = 7/60? Please explain me.
(37)

Dibyanshu said:   3 years ago
A - 15 days.
B - 20 days.

LCM of 15 & 20 is 60 (The total work is 60 also).

So,

The Efficiency of one day's work is 60/15 = 4 and 60/20 = 3.

Then, both A & B can complete the work in one day is 4+3=7.

They worked for 4 days, so 7x4=28
Work completed in 4days by both A+B=28.
Then, rest work = Total work - Completed work
Rest work = 60-28=32.
32/60 = 8/15
The answer is = 8/15.
(233)

VisHnu RaM said:   4 years ago
Thank you for giving the clear explanation @Swetha.

And 60 will come, No of days LCM

15 days to 15 * 4 = 60.
20 days to 20 * 3 = 60.

So, the LCM is 60.
(13)

Swetha said:   4 years ago
First of all, thank you to explain the method.

I have a doubt that how we know to take (i.e Total work = 60)?

Anyone, please help me to get it.
(6)

AKT said:   4 years ago
Thanks everyone for explaining the answer.
(3)

Ankita said:   4 years ago
@Jyoti.

It's 1 -7/15 as it is asking how much work is left. Which means 1 is the total amount of work, and 7/15 is the amount of work completed.

So, to get the remaining work we hv to subtract the work done by the whole work. Which is
1-7/15.
= 15/15 - 7/15.
= 15-7/15.
= 8/15.
Hope it helps.
(15)

Jyothi said:   4 years ago
I am not getting. How 1-7/15? Explain, please.
(3)