A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 35 of 35.
Sundar said:
1 decade ago
@Poorni:
The total work = 1;
Work done by A and B in 4 days = 7/15.
Therefore, the pending work = 1 - 7/15 = 0.533333333... (or) 8/15.
Hope this help you. Have a nice day!
The total work = 1;
Work done by A and B in 4 days = 7/15.
Therefore, the pending work = 1 - 7/15 = 0.533333333... (or) 8/15.
Hope this help you. Have a nice day!
(1)
Appu said:
1 decade ago
@Deepa
(1/50+1/20) = (20+15)/300 //This get by cross multiplication.
= 35/300
= 7/60.
I think your doubt is clear now.
(1/50+1/20) = (20+15)/300 //This get by cross multiplication.
= 35/300
= 7/60.
I think your doubt is clear now.
(1)
Deepa said:
1 decade ago
Can you explain how 7/60 came?
(2)
Poorni said:
1 decade ago
Why (1 - 7/15)?