Discussion Forum : Time and Work - General Questions (Q.No. 29)
29.
A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
53 comments Page 4 of 6.

Pawan narkhede said:   1 decade ago
How to come A is 7/4 times efficient than B?

Sunil kumar said:   1 decade ago
Efficiency ratio is 7:4.

Time ratio is 4:7.

Work ratio is inversely proportional to time ratio.

Here A is more efficient so A's time is less, B is less efficient than a so B take more time than A.

So both take 28 days (7 + 4) 11 ---- 28.

11/7*28 = 11*4 = 44 days.

So answer is 44 days.

D JOHN said:   1 decade ago
A and B can do a work in 28 days. A is 7/4 efficient than B. If B done the work in how many days. Please explain friends.

Iovd said:   1 decade ago
@Raj.

They given 1*3/4 in example after solving it we get 7/4(4*1+3).

Raj said:   1 decade ago
How we get A =7/4? Please help me.

Pari said:   1 decade ago
GIVEN : A=7/4B, THEREFORE B = 4/7A.

A + B = 1/7.
A + 4/7A = 1/7.
11/7A = 1/7.
A = I/7*7/11 = 1/11.

Hence 11 days.
Hope this is a correct way.

Divi said:   1 decade ago
A is 7/4 efficient than B means A=7/4B =>B=4/7A.

A and B together can complete the work in 7 days.
[i.e.Time is directly proportional to work => 7days=work => 1 day=1/7th work].

So,

A + B = 1/7.
A + 4/7A= 1/7.
11/7A = 1/7.
A = 1/11.

Hence, A alone can work for 11 days.

Chara said:   1 decade ago
A's working capacity = X.
B's working capacity = Y.

Given, X + Y = 1/30 ................equation(1).

Also, X = 7/4 Y

i.e.. Y= 4/7 X .................equation (2).

PUTTING Y=4/7X from eqtn (2) in Eqtn(1), we get,

X= 1/11.

i.e.. A working capacity is 1/11( interpretation: "A" can do 1 work in 11 days).

SHIVAM RANA said:   1 decade ago
As A = 7/4B-------(1).

=> A+B GIVES WORK DONE IN 7 DAYS.
=> Unity gives that work in 7*(A+B) DAYS.

=> Using (1).
=> A gives that work in (7*(A+4/7A))/A DAYS.
=> 11 DAYS.

THIVYA said:   1 decade ago
A and B collectively can do the work in 7 days.
so their one day work is 1/7.

A+B = 1/7-------(1).
A is 7/4 times efficient than B which means.

A = (7/4)B ----------(2).
or
B = (4/7)A ------------(2).

Put 2 int 1 eq,
A+(4/7)A = 1/7.
A(11/7) = 1/7.

SO,
A CAN COMPLETE THE PIECE OF WORK IN 11 DAYS.