Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 29)
29.
A and B can do a job together in 7 days. A is 1
times as efficient as B. The same job can be done by A alone in :

Answer: Option
Explanation:
(A's 1 day's work) : (B's 1 day's work) = | 7 | : 1 = 7 : 4. |
4 |
Let A's and B's 1 day's work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | ![]() |
1 | ![]() |
1 | . |
7 | 7 | 77 |
![]() |
![]() |
1 | x 7 | ![]() |
= | 1 | . |
77 | 11 |
Discussion:
53 comments Page 3 of 6.
Shadab Akhtar said:
9 years ago
@priya & siri, 7/4 is given in question itself, when you will solve the fraction part you will get it.
A+B = 1/7 (given). 1.
A = 7/4*B (given). 2.
B = 4A/7 (from 2).
Put the value of B in eq 1.
A+4A/7 = 1/7.
A = 1/11.
So A will do the work in 11 days.
A+B = 1/7 (given). 1.
A = 7/4*B (given). 2.
B = 4A/7 (from 2).
Put the value of B in eq 1.
A+4A/7 = 1/7.
A = 1/11.
So A will do the work in 11 days.
(2)
Siri said:
9 years ago
How you are getting 7/4? Anybody explain it please.
Priya said:
9 years ago
I didn't get why 7/4 is used?
Please explain.
Please explain.
RAHUL ROY said:
9 years ago
Step 1.
One day work of A and B, (A + B) = 1/7 ----> (1)
Step 2.
A:B =4:7, according to time not work.
Step 3.
Let assume A and B one day work be 1/4x and 1/7x.
Now, put the value of A and B in equation (1).
A + B = 1/4x + 1/7x.
=1/7 and getting x value as 11/4.
Step 4.
Put the value of x in A's 1-day work, 4x = 4X(11/4) =11.
One day work of A and B, (A + B) = 1/7 ----> (1)
Step 2.
A:B =4:7, according to time not work.
Step 3.
Let assume A and B one day work be 1/4x and 1/7x.
Now, put the value of A and B in equation (1).
A + B = 1/4x + 1/7x.
=1/7 and getting x value as 11/4.
Step 4.
Put the value of x in A's 1-day work, 4x = 4X(11/4) =11.
Vinnu said:
9 years ago
Given: A is 7/4 times as efficient as B.
A:B = 7/4:1 => A:B = 7:4(the ratio is in terms of efficiency).
As we know that efficiency is indirectly porporational time taken to finish the work done.
A:B = 4:7(the ratio is in terms of time taken to finish the work).
A+B = 7 (this is the time taken to finish the work together).
=> B = 7-A substituting in above equation.
=> A:(7-A) = 4:7.
=> A/7-A = 4/7.
=> 7A = 4(7-A).
=> 7A = 28-4A
=> 7A+4A = 28.
=> 11A = 28.
=> A = 28/11.
=> A = 2 6/11 is the answer.
A:B = 7/4:1 => A:B = 7:4(the ratio is in terms of efficiency).
As we know that efficiency is indirectly porporational time taken to finish the work done.
A:B = 4:7(the ratio is in terms of time taken to finish the work).
A+B = 7 (this is the time taken to finish the work together).
=> B = 7-A substituting in above equation.
=> A:(7-A) = 4:7.
=> A/7-A = 4/7.
=> 7A = 4(7-A).
=> 7A = 28-4A
=> 7A+4A = 28.
=> 11A = 28.
=> A = 28/11.
=> A = 2 6/11 is the answer.
Adithya vinay kumar said:
9 years ago
How come efficiency is directly proportional to the no of days worked?
Kuntal said:
10 years ago
a : b if work ratio is 7 : 4 then time ratio is 4 : 7.
Let a takes 4x and b takes 7x days.
So 1 days total work 1/4x + 1/7x = 1/7.
So here we get x = 11/4.
So a takes 4x = 4*11/4 = 11 days.
Let a takes 4x and b takes 7x days.
So 1 days total work 1/4x + 1/7x = 1/7.
So here we get x = 11/4.
So a takes 4x = 4*11/4 = 11 days.
(1)
Krishna mohan said:
10 years ago
Given, A+B = 1/7 ------(1).
And A = 7/4B (A is 13/4 times as efficient as B).
Sub A = 7/4B in (1).
We get B = 4/77---- (2).
Then Sub (2) in (1).
We get A = 1/11 (which means A can complete work in 11 days).
And A = 7/4B (A is 13/4 times as efficient as B).
Sub A = 7/4B in (1).
We get B = 4/77---- (2).
Then Sub (2) in (1).
We get A = 1/11 (which means A can complete work in 11 days).
Govinda said:
10 years ago
Why 7/4 explain guys?
Vembarasi pandiyan said:
1 decade ago
Here efficiency is given so we have to change efficiency into time but in this this why the efficiency is not change I want to know the reason please explain it. 7/4:1=7x:4x this is efficiency 4x:7x this is the time in this question why we are not change the efficiency into time.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers