Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 29)
29.
A and B can do a job together in 7 days. A is 1
times as efficient as B. The same job can be done by A alone in :

Answer: Option
Explanation:
(A's 1 day's work) : (B's 1 day's work) = | 7 | : 1 = 7 : 4. |
4 |
Let A's and B's 1 day's work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | ![]() |
1 | ![]() |
1 | . |
7 | 7 | 77 |
![]() |
![]() |
1 | x 7 | ![]() |
= | 1 | . |
77 | 11 |
Discussion:
53 comments Page 1 of 6.
Vinnu said:
9 years ago
Given: A is 7/4 times as efficient as B.
A:B = 7/4:1 => A:B = 7:4(the ratio is in terms of efficiency).
As we know that efficiency is indirectly porporational time taken to finish the work done.
A:B = 4:7(the ratio is in terms of time taken to finish the work).
A+B = 7 (this is the time taken to finish the work together).
=> B = 7-A substituting in above equation.
=> A:(7-A) = 4:7.
=> A/7-A = 4/7.
=> 7A = 4(7-A).
=> 7A = 28-4A
=> 7A+4A = 28.
=> 11A = 28.
=> A = 28/11.
=> A = 2 6/11 is the answer.
A:B = 7/4:1 => A:B = 7:4(the ratio is in terms of efficiency).
As we know that efficiency is indirectly porporational time taken to finish the work done.
A:B = 4:7(the ratio is in terms of time taken to finish the work).
A+B = 7 (this is the time taken to finish the work together).
=> B = 7-A substituting in above equation.
=> A:(7-A) = 4:7.
=> A/7-A = 4/7.
=> 7A = 4(7-A).
=> 7A = 28-4A
=> 7A+4A = 28.
=> 11A = 28.
=> A = 28/11.
=> A = 2 6/11 is the answer.
Padma said:
8 years ago
Efficiency of A:B = 7/4k : k.
No of days taken by A: B = 4k/7k = 4/7 (no of days taken = ratio of the reciprocals of the efficiency).
Let the work done in one day = 1/s.
then , work done by A in one day = 4/s.
work done by B in one day = 7/s.
work done by A+B = 1/7.
4/s + 7/s = 1/7.
11/s = 1/7.
s= 77.
Work done by A in one day = 4/s.
= 4/77.
the efficiency of A = 7/4.
Hence, work done by A in one day = 4/77 * 7/4.
= 1/11
Thus, A can do the job in 11 days.
No of days taken by A: B = 4k/7k = 4/7 (no of days taken = ratio of the reciprocals of the efficiency).
Let the work done in one day = 1/s.
then , work done by A in one day = 4/s.
work done by B in one day = 7/s.
work done by A+B = 1/7.
4/s + 7/s = 1/7.
11/s = 1/7.
s= 77.
Work done by A in one day = 4/s.
= 4/77.
the efficiency of A = 7/4.
Hence, work done by A in one day = 4/77 * 7/4.
= 1/11
Thus, A can do the job in 11 days.
(1)
Torres Dungs said:
1 decade ago
I think this would be an easy approach:
A=7/4B (A is as efficient as 1*3/4 times as B).
=> On cross multiplying we get, 4A=7B-----------> 1.
=> From question, A+B=1/7 (A,B is one days work so equating to 1/7).
Therefore again cross multiply,
We get, 7A+7B = 1.
=>from 1, we have 4A=7B.
So substitute 4A in 7B.
We get,
7A+4A=1 ==>11A=1===> A=1/11(which is A's one day's work).
Hence,
Total days A need==> 11 days.
Hope you'd have undersTood :).
A=7/4B (A is as efficient as 1*3/4 times as B).
=> On cross multiplying we get, 4A=7B-----------> 1.
=> From question, A+B=1/7 (A,B is one days work so equating to 1/7).
Therefore again cross multiply,
We get, 7A+7B = 1.
=>from 1, we have 4A=7B.
So substitute 4A in 7B.
We get,
7A+4A=1 ==>11A=1===> A=1/11(which is A's one day's work).
Hence,
Total days A need==> 11 days.
Hope you'd have undersTood :).
Sourav Kalal said:
4 years ago
Here is my simple approach
------------------------------------
A=7 (A's 1 day work)
B=4 (B's 1 day work)
------------------------------------
A+B = 11 (A+B's 1 day work).
A+B can finish work in 7 days,
So, Total work = 11*7=77 unit.
A can do 7 units of work in 1 day.
for 77 unit he will take 77/7= 11 days.
(7 ----> 1,
77 ---> ?) = 77/7.
------------------------------------
A=7 (A's 1 day work)
B=4 (B's 1 day work)
------------------------------------
A+B = 11 (A+B's 1 day work).
A+B can finish work in 7 days,
So, Total work = 11*7=77 unit.
A can do 7 units of work in 1 day.
for 77 unit he will take 77/7= 11 days.
(7 ----> 1,
77 ---> ?) = 77/7.
(22)
RAHUL ROY said:
9 years ago
Step 1.
One day work of A and B, (A + B) = 1/7 ----> (1)
Step 2.
A:B =4:7, according to time not work.
Step 3.
Let assume A and B one day work be 1/4x and 1/7x.
Now, put the value of A and B in equation (1).
A + B = 1/4x + 1/7x.
=1/7 and getting x value as 11/4.
Step 4.
Put the value of x in A's 1-day work, 4x = 4X(11/4) =11.
One day work of A and B, (A + B) = 1/7 ----> (1)
Step 2.
A:B =4:7, according to time not work.
Step 3.
Let assume A and B one day work be 1/4x and 1/7x.
Now, put the value of A and B in equation (1).
A + B = 1/4x + 1/7x.
=1/7 and getting x value as 11/4.
Step 4.
Put the value of x in A's 1-day work, 4x = 4X(11/4) =11.
Chara said:
1 decade ago
A's working capacity = X.
B's working capacity = Y.
Given, X + Y = 1/30 ................equation(1).
Also, X = 7/4 Y
i.e.. Y= 4/7 X .................equation (2).
PUTTING Y=4/7X from eqtn (2) in Eqtn(1), we get,
X= 1/11.
i.e.. A working capacity is 1/11( interpretation: "A" can do 1 work in 11 days).
B's working capacity = Y.
Given, X + Y = 1/30 ................equation(1).
Also, X = 7/4 Y
i.e.. Y= 4/7 X .................equation (2).
PUTTING Y=4/7X from eqtn (2) in Eqtn(1), we get,
X= 1/11.
i.e.. A working capacity is 1/11( interpretation: "A" can do 1 work in 11 days).
Vaibhav jain said:
9 years ago
Let,
A = x.
B = 7/4x.
Total work = 7x (i.e. Lcm of A &B).
A's one day work = 7.
B's one day work = 4.
(A + B)'s one day work = 11.
As we know that total work we have 7x.
Using formula of work --->(total work/(A+B) one day work) = (A+B) total work.
7x/11 = 7--->x=7*11/7--> x = 11 i.e total days of x.
A = x.
B = 7/4x.
Total work = 7x (i.e. Lcm of A &B).
A's one day work = 7.
B's one day work = 4.
(A + B)'s one day work = 11.
As we know that total work we have 7x.
Using formula of work --->(total work/(A+B) one day work) = (A+B) total work.
7x/11 = 7--->x=7*11/7--> x = 11 i.e total days of x.
THIVYA said:
1 decade ago
A and B collectively can do the work in 7 days.
so their one day work is 1/7.
A+B = 1/7-------(1).
A is 7/4 times efficient than B which means.
A = (7/4)B ----------(2).
or
B = (4/7)A ------------(2).
Put 2 int 1 eq,
A+(4/7)A = 1/7.
A(11/7) = 1/7.
SO,
A CAN COMPLETE THE PIECE OF WORK IN 11 DAYS.
so their one day work is 1/7.
A+B = 1/7-------(1).
A is 7/4 times efficient than B which means.
A = (7/4)B ----------(2).
or
B = (4/7)A ------------(2).
Put 2 int 1 eq,
A+(4/7)A = 1/7.
A(11/7) = 1/7.
SO,
A CAN COMPLETE THE PIECE OF WORK IN 11 DAYS.
UMESH PRASAD said:
1 decade ago
A and B collectively can do the work in 7 days
so their one day work is 1/7
A+B=1/7-------(1)
A is 7/4 times efficient then B which means
A=(7/4)B ----------
or
B=(4/7)A ------------(2)
put the value of (2)in (1)
(4/7)*B+B=1/7
B=1/11 THIS IS HIS ONE DAY WORK
ALONE B CAN FINISH IN 11 DAY
so their one day work is 1/7
A+B=1/7-------(1)
A is 7/4 times efficient then B which means
A=(7/4)B ----------
or
B=(4/7)A ------------(2)
put the value of (2)in (1)
(4/7)*B+B=1/7
B=1/11 THIS IS HIS ONE DAY WORK
ALONE B CAN FINISH IN 11 DAY
Divi said:
1 decade ago
A is 7/4 efficient than B means A=7/4B =>B=4/7A.
A and B together can complete the work in 7 days.
[i.e.Time is directly proportional to work => 7days=work => 1 day=1/7th work].
So,
A + B = 1/7.
A + 4/7A= 1/7.
11/7A = 1/7.
A = 1/11.
Hence, A alone can work for 11 days.
A and B together can complete the work in 7 days.
[i.e.Time is directly proportional to work => 7days=work => 1 day=1/7th work].
So,
A + B = 1/7.
A + 4/7A= 1/7.
11/7A = 1/7.
A = 1/11.
Hence, A alone can work for 11 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers