Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 29)
29.
A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
53 comments Page 5 of 6.

Girish said:   1 decade ago
Why we should multiply by 7 at the end ?

Pradeep Oram said:   1 decade ago
Given: A+B = 1/7......(1).

And A = 7/4B (efficient than B).

Put in(1). We get.

B=4/77(work of B).

Then,

Work of A = (1/7)-(4/77) = 7/77 = 1/11 (from eq.(1)).

So, A finish job in 11 days.

Torres Dungs said:   1 decade ago
I think this would be an easy approach:

A=7/4B (A is as efficient as 1*3/4 times as B).

=> On cross multiplying we get, 4A=7B-----------> 1.
=> From question, A+B=1/7 (A,B is one days work so equating to 1/7).

Therefore again cross multiply,
We get, 7A+7B = 1.

=>from 1, we have 4A=7B.
So substitute 4A in 7B.

We get,
7A+4A=1 ==>11A=1===> A=1/11(which is A's one day's work).

Hence,
Total days A need==> 11 days.

Hope you'd have undersTood :).

Heena said:   1 decade ago
@nidhi
if A=(7/4)B
then Eq2 should be
7/4(B)+B=1/7

Jimmy John said:   1 decade ago
A+B=1/7
7A+7B=1-----1

A=7/4B
4A=7B-----2

sub 2 in 1
7A+4A=1 (Since 7B=4A)
therefore 11A=1
A=1/11

therefore A can finish in 11 days
(1)

Varun said:   1 decade ago
Ratio type problem solve by 'x' value.

Nidhi said:   1 decade ago
A and B collectively can do the work in 7 days.

So their one day work is 1/7.

A+B=1/7-- (1).

A is 7/4 times efficient then B which means.

A= (7/4) B.

Or.

B= (4/7) A - (2).

Put the value of (2) in (1).

(4/7) *B+B=1/7.

B=1/11 THIS IS HIS ONE DAY WORK.

ALONE B CAN FINISH IN 11 DAY.

UMESH PRASAD said:   1 decade ago
A and B collectively can do the work in 7 days
so their one day work is 1/7
A+B=1/7-------(1)
A is 7/4 times efficient then B which means

A=(7/4)B ----------
or
B=(4/7)A ------------(2)
put the value of (2)in (1)
(4/7)*B+B=1/7

B=1/11 THIS IS HIS ONE DAY WORK
ALONE B CAN FINISH IN 11 DAY

Pankaj said:   1 decade ago
How Total Working Days=7*4=28 ?

M.vignesh said:   1 decade ago
A=7/4
B=1
A:B=7/4:1
So A:b=7:4
Total Working Days=7*4=28
a=28/7=4
b=28/4=7
a=a+b
a=4+7=11
A alone=11


Post your comments here:

Your comments will be displayed after verification.