5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 9 of 19.

Chandni said:   1 decade ago
Any one help me in above question we take difference of day like 3-1 equal to 2 than why we not take difference of day 8-6 equal to 2 please help me.

Prashant khair said:   4 years ago
C's share = total or given profit (money-3200) * (c's ratio(1/24)/sum of all ratios(3)
= 3200*3/24.

(NOTE : Sum of all ratios = 1/8 +1/6 + 1/24).
(9)

Maruthupandian said:   1 decade ago
@Arnab.

In your explanation how do you do this (24/7-3) for calculating days of C alone?

won't it be (3-24/7) ?

because (A+B+C)-(A+B) = C.

Kartik Choudhary said:   9 years ago
Please make me understand this.

We calculated ratio 4:3:1.
But how's the last step is done?
How we calculated C's share. Please elaborate it.

Sai Mounika said:   1 decade ago
Why we are multiply all by 24? I think C's 1 day work is 1/24 so we have to multiply all by 24 in order to get the 3 days work. Am I right?

Adithya said:   1 decade ago
A's wages : B's wages : C's wages = 4 : 3 : 1.
so
total wages(4+3+1)
3200/8 =400
for A = 400*4 = 1600....B = 3*400=1200.
for C =400

Naman said:   1 decade ago
This is very easy to understand .....

in last line....
there wages is 4:3:1 ....so wage of c is..
===1*3200/(4+3+1)====3200/8===400

Suba said:   1 decade ago
There's no need of multiplying the number with 3. We can do it in other way as well.

As @Sai vinay said, we can consider that part.

Shaju said:   2 decades ago
Can anyone help me with the last step?

If we need to calculate (3 x 1/24 x 3200) then what was the use of finding the ratio.
(1)

Keerthana said:   2 years ago
1/6 + 1/8 + 1/C = 1/3.
1/C = 7/24-1/3.
1/C = 1/24( 1 day's work of C).
3 days work of C-->3/24= 1/8.
1/8 x 3200 = ₹400.