Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Answer: Option
Explanation:
C's 1 day's work = | 1 | - | ![]() |
1 | + | 1 | ![]() |
= | 1 | - | 7 | = | 1 | . |
3 | 6 | 8 | 3 | 24 | 24 |
A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
6 | 8 | 24 |
![]() |
![]() |
3 x | 1 | x 3200 | ![]() |
= Rs. 400. |
24 |
Discussion:
179 comments Page 1 of 18.
HARIPRASAD K N said:
6 years ago
It is very simple;
A's 1day work = 1/6.
B's 1day work = 1/8.
A&B&C's 1day work=1/3.
C's 1day work=A+B+C'S 1day work-(A+B's 1day work)=(1/3)-(1/6)-(1/8) = 1/24.
A will do a complete work that is 1 full work in 6 day's means how much work he will do in 3 days given by;
6days--------->1 complete work
3days--------->?
Cross multiply then we get 1/2 work that is half of the work total work done by A.
Similarly, B ' s work done in 3 days is given by;
8 days-------->1 complete work,
3------------------?
Cross multiply we get 3/8 part of 1 complete work done by B.
Similarly, C's part of work is given by;
24 days --------->1 complete work
3 days ------------>?
By cross multiply, we get 1/8.
So,
For 1 complete work they get ------------>3200.
Then for A's (1/2) part of that work------>?
Cross multiply we get 1600.
Similarly for B
1 complete work------->3200
B's (3/8) part of the work--->?
By cross multiply, we get 1200.
Similarly for C.
1 Complete work ------>3200
C's part of (1/8) part of the work--->?
We get by cross multiply 400.
A's 1day work = 1/6.
B's 1day work = 1/8.
A&B&C's 1day work=1/3.
C's 1day work=A+B+C'S 1day work-(A+B's 1day work)=(1/3)-(1/6)-(1/8) = 1/24.
A will do a complete work that is 1 full work in 6 day's means how much work he will do in 3 days given by;
6days--------->1 complete work
3days--------->?
Cross multiply then we get 1/2 work that is half of the work total work done by A.
Similarly, B ' s work done in 3 days is given by;
8 days-------->1 complete work,
3------------------?
Cross multiply we get 3/8 part of 1 complete work done by B.
Similarly, C's part of work is given by;
24 days --------->1 complete work
3 days ------------>?
By cross multiply, we get 1/8.
So,
For 1 complete work they get ------------>3200.
Then for A's (1/2) part of that work------>?
Cross multiply we get 1600.
Similarly for B
1 complete work------->3200
B's (3/8) part of the work--->?
By cross multiply, we get 1200.
Similarly for C.
1 Complete work ------>3200
C's part of (1/8) part of the work--->?
We get by cross multiply 400.
(1)
Sunil said:
7 years ago
Option A is the right answer if you perfectly have understood the question.
Here in the question, it is given that A & B undertook to do the work for 3200 then how C can earn his wages from the first day.
Here Supposed A & B if do the work in 3 days then they will able to do - 21 work
But they did it in 3 days with the help of C.
So the method is here that;
For the first two days, A+B do - 14 work.
Then with the help of C they able to finish it in 3 days so A+B+C do last day - 10 work.
That means one-day work of C is - 3.
Then the work ratio of A+B for two days with A+B+C in one day is - 14:10 = 7:5.
Then (3200 ÷12) * 5 = 1250.
Then bye one-day work ratio of A B&C = 4:3:3.
Then (3200÷10) * 3 = 375,
Hence the answer is 375.
Here in the question, it is given that A & B undertook to do the work for 3200 then how C can earn his wages from the first day.
Here Supposed A & B if do the work in 3 days then they will able to do - 21 work
But they did it in 3 days with the help of C.
So the method is here that;
For the first two days, A+B do - 14 work.
Then with the help of C they able to finish it in 3 days so A+B+C do last day - 10 work.
That means one-day work of C is - 3.
Then the work ratio of A+B for two days with A+B+C in one day is - 14:10 = 7:5.
Then (3200 ÷12) * 5 = 1250.
Then bye one-day work ratio of A B&C = 4:3:3.
Then (3200÷10) * 3 = 375,
Hence the answer is 375.
Taran said:
7 years ago
@All.
It is simple by solving this way.
Work = efficiency*time ----> 1
Efficiency = work/time. ----> 2
Time = work/efficiency ----> 3
Acc to question;
A can do work in 6 days.
B can do work in 8 days.
(A+B+C) Can do work in 3 days.
Taking LCM of 6,8,3 is 24.
Hence Let Work =24 units.
Now efficiency of A=24/6= 4units/day ----> using(2)
Efficiency of B=24/8= 3 units/day ----> using(2)
Efficiencyof (A+B+C) = 24/3=8unit/day ----> using(2)
Hence efficiency of C=Efficiency of (A+B+C)-Efficiency of A -Efficiency of B= 8-4-3=1unit/day.
Now we know A:B:C::4:3:1.
Let x be the price for 1 unit of work.
SO 4x+3x+x=3200.
8x=3200.
X=3200/8 =400.
As we know C can do 1unit/day.
Hence wages for C =1x(and x=400).
Hence it's 400.
It is simple by solving this way.
Work = efficiency*time ----> 1
Efficiency = work/time. ----> 2
Time = work/efficiency ----> 3
Acc to question;
A can do work in 6 days.
B can do work in 8 days.
(A+B+C) Can do work in 3 days.
Taking LCM of 6,8,3 is 24.
Hence Let Work =24 units.
Now efficiency of A=24/6= 4units/day ----> using(2)
Efficiency of B=24/8= 3 units/day ----> using(2)
Efficiencyof (A+B+C) = 24/3=8unit/day ----> using(2)
Hence efficiency of C=Efficiency of (A+B+C)-Efficiency of A -Efficiency of B= 8-4-3=1unit/day.
Now we know A:B:C::4:3:1.
Let x be the price for 1 unit of work.
SO 4x+3x+x=3200.
8x=3200.
X=3200/8 =400.
As we know C can do 1unit/day.
Hence wages for C =1x(and x=400).
Hence it's 400.
(1)
DivyaBatra said:
8 years ago
We are multiplying 3200 with 3 because of this reason:
See, A and B worked together and got 3200 for their work. But with the help of C, they could finish their work in 3 days. So, as we can see" with the help of C", so, C 's share is also given by both A and B as A and B has taken help from C.
So, C's share is calculated like this:-.
C's 1 day's work=1/24.
But if we do this:- 3200*1/24; this will be wrong as C will get wages for his 1 day work only.
But given in question that C has worked for 3 days, so 3200*1/24*3= i.e. 3 will also be multiplied, so to give C's share to him completely.
So, answer is 3200*1/24*3=400.
See, A and B worked together and got 3200 for their work. But with the help of C, they could finish their work in 3 days. So, as we can see" with the help of C", so, C 's share is also given by both A and B as A and B has taken help from C.
So, C's share is calculated like this:-.
C's 1 day's work=1/24.
But if we do this:- 3200*1/24; this will be wrong as C will get wages for his 1 day work only.
But given in question that C has worked for 3 days, so 3200*1/24*3= i.e. 3 will also be multiplied, so to give C's share to him completely.
So, answer is 3200*1/24*3=400.
Sai said:
6 years ago
A = 6days.
B = 8days.
A+B+C=3days.
C's no of days required to complete the work.
(1÷6)+(1÷8)+(1÷C)=(1÷3).
Therefore C=24 day's.
Now the ratio of no of days taken by each member to complete the work comes(6:8:24).
But, we know that A is somewhat a fast worker than B and C therefore he must be paid more and C is taking more time he must be paid less,
Now let's considers these people's each day of work ie A=(1÷6), B=(1÷8), C=(1÷24).
Therefore the total units of work=(1÷6)+(1÷8)+(1÷24)=( 1÷3) by taking lcm
Now ,
The total amount to is 3200.
3200/(1÷3)=9600.
Therefore 9600/24 is 400.
B = 8days.
A+B+C=3days.
C's no of days required to complete the work.
(1÷6)+(1÷8)+(1÷C)=(1÷3).
Therefore C=24 day's.
Now the ratio of no of days taken by each member to complete the work comes(6:8:24).
But, we know that A is somewhat a fast worker than B and C therefore he must be paid more and C is taking more time he must be paid less,
Now let's considers these people's each day of work ie A=(1÷6), B=(1÷8), C=(1÷24).
Therefore the total units of work=(1÷6)+(1÷8)+(1÷24)=( 1÷3) by taking lcm
Now ,
The total amount to is 3200.
3200/(1÷3)=9600.
Therefore 9600/24 is 400.
RAVI KUMAR said:
10 years ago
From given:
A+B+C can complete a work in 3 days and they will get amount 3200 for 3 days.
So A, B, C work for 3 days.
A one day work is 1/6.
B one day work is 1/8.
C one day work is, we have to find out.
A+B+C one day work is 1/3 because A, B, C complete a work in 3 days.
So A+B+C one day work = 1/6+1/8+1/C.
1/3 = 1/6+1/8+1/C.
1/C = 1/24 so "C" one day work is 1/24.
A's 3 days work is 3/6 and he will get the amount is 3/6*3200 = 1600.
B's 3 day work is 3/8 and he will get 3/8*3200 = 1200.
C's 3 day work is 3/24 and he will get 3/24*3200 = 400.
A+B+C can complete a work in 3 days and they will get amount 3200 for 3 days.
So A, B, C work for 3 days.
A one day work is 1/6.
B one day work is 1/8.
C one day work is, we have to find out.
A+B+C one day work is 1/3 because A, B, C complete a work in 3 days.
So A+B+C one day work = 1/6+1/8+1/C.
1/3 = 1/6+1/8+1/C.
1/C = 1/24 so "C" one day work is 1/24.
A's 3 days work is 3/6 and he will get the amount is 3/6*3200 = 1600.
B's 3 day work is 3/8 and he will get 3/8*3200 = 1200.
C's 3 day work is 3/24 and he will get 3/24*3200 = 400.
Seema duhan said:
1 decade ago
take LCM of A and B work, then get:
A+B=7/24.
WHERE:
A+B+C = 1/3 (given).
So 7/24+C=1/3.
C=1/24.
With the ratio you would get to know the share of A, B and C.
Now the Ratio of A:B:C =1/6:1/8:1/24 (The L.C.M Of 1/6+1/8+1/24 is 24)
A:B:C =4:3:1.
So the wages can be calculated easily (4*400:3*400:1*400) which is equal to (1600:1200:400) if we add it, it would give us the total amount if 3200.
It is simple, A's share is (4/8)*3200.
B's share is (3/8)*3200.
C's share is (1/8)*3200 (because 4+3+1=8).
A+B=7/24.
WHERE:
A+B+C = 1/3 (given).
So 7/24+C=1/3.
C=1/24.
With the ratio you would get to know the share of A, B and C.
Now the Ratio of A:B:C =1/6:1/8:1/24 (The L.C.M Of 1/6+1/8+1/24 is 24)
A:B:C =4:3:1.
So the wages can be calculated easily (4*400:3*400:1*400) which is equal to (1600:1200:400) if we add it, it would give us the total amount if 3200.
It is simple, A's share is (4/8)*3200.
B's share is (3/8)*3200.
C's share is (1/8)*3200 (because 4+3+1=8).
Arnab said:
1 decade ago
A lot simpler method --
A does 1/6 in 1 day.. B does 1/8 in one day..So they both do (1/6+1/8=7/24)in 1 day.. Hence they will finish the work in 24/7 days..
they get paid 3200 for 24/7 units of work..hence they'll be paid 3200*7/24 for 1 units of work..which is equal to 2800/3..
now A and B were finishing it in 24/7 days but on C's help they do it in 3 days..hence they are saved 24/7-3 units of work which is equal to 3/7 units of works and C will be paid for this..now 1 unit's pay was 2800/3..hence 3/7 units pay is (2800*3)/(3*7) = 400!!
A does 1/6 in 1 day.. B does 1/8 in one day..So they both do (1/6+1/8=7/24)in 1 day.. Hence they will finish the work in 24/7 days..
they get paid 3200 for 24/7 units of work..hence they'll be paid 3200*7/24 for 1 units of work..which is equal to 2800/3..
now A and B were finishing it in 24/7 days but on C's help they do it in 3 days..hence they are saved 24/7-3 units of work which is equal to 3/7 units of works and C will be paid for this..now 1 unit's pay was 2800/3..hence 3/7 units pay is (2800*3)/(3*7) = 400!!
BHK said:
1 year ago
1. A can do in 6 days => 6
2. B can do in 8 days => 8 LCM of 6,8,3 is 48
3. A+B+C an do in 3 days => 3
=>Individual efficiency is;
A's 48/6 => 8 , B's 48/8 => 6 , A+B+C's =>48/3 => 16
=> Now the ratio is A:B:C = 8:6:16.
i.e .., A:B:C = 4:3:8.
Since the above ratio, C's is (4+3)-8=1.
=> New ratio is A:B: C = 4:3:1.
We have to find out how much to be paid for work.
1/8*3200 => 400.
2. B can do in 8 days => 8 LCM of 6,8,3 is 48
3. A+B+C an do in 3 days => 3
=>Individual efficiency is;
A's 48/6 => 8 , B's 48/8 => 6 , A+B+C's =>48/3 => 16
=> Now the ratio is A:B:C = 8:6:16.
i.e .., A:B:C = 4:3:8.
Since the above ratio, C's is (4+3)-8=1.
=> New ratio is A:B: C = 4:3:1.
We have to find out how much to be paid for work.
1/8*3200 => 400.
(21)
Archita said:
1 decade ago
A 1 day work = 1/6.
B 1 day work = 1/8.
(A + B + C) complete work in = 3 days.
A + B + C one day work = 1/3.
1/6 + 1/8 + (C one day work) = 1/3.
C one day work = 1/3 - (1/6 + 1/8) = 1/24.
Total money = 3200.
So A, B, C share in the whole money is depend on their work ratio.
A work : B work : C work = 1/6 : 1/8 : 1/24.
Or 4 : 3 : 1 (multiply 24 in each).
A share = (4/8) *3200 = 1600.
B share = (3/8) * 3200 = 1200.
C share = (1/8) *3200 = 400.
B 1 day work = 1/8.
(A + B + C) complete work in = 3 days.
A + B + C one day work = 1/3.
1/6 + 1/8 + (C one day work) = 1/3.
C one day work = 1/3 - (1/6 + 1/8) = 1/24.
Total money = 3200.
So A, B, C share in the whole money is depend on their work ratio.
A work : B work : C work = 1/6 : 1/8 : 1/24.
Or 4 : 3 : 1 (multiply 24 in each).
A share = (4/8) *3200 = 1600.
B share = (3/8) * 3200 = 1200.
C share = (1/8) *3200 = 400.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers