5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 7 of 18.

Prince dubey said:   1 decade ago
Wages ratio is not important short method is.

C work in 3 days.

A & B money = 3200.

C work ratio is 1/24 by method (1/3- (1/6+1/8) ).

Last calculation is 3*1/24*3200.

Answer is 400.

HimiD said:   8 years ago
We see that C can finish it in 3 days. So, C works harder. If we divide Rs 3200 by 3 its Rs 1066.67. As C works harder C should get more than Rs. 1066.67. So, why he is getting Rs. 400?

Kartik said:   9 months ago
The Lcm of 6 and 8 is 24(total work) the A = 4 and B = 3.
Given 3(A+B+C) = 24.
By substituting A and B values C = 1.
The ratios of A, B, C are 4:3:1.
C's share is = 1/8 × 3200 = 400.
(39)

Praveen kumar said:   7 years ago
The sum of three numbers is 275. If the ratio between the fast and second be 3:7 and that between the second and third be 4:5 then find the second number. Can anyone solve this?

Rahul chourasia said:   1 decade ago
Wages ratio is not important short method is
c work in 3 days
a & b money =3200
c work ratio is 1/24 by method (1/3-(1/6+1/8))
last calculation is 3*1/24*3200
ans is 400

Vasanth said:   9 years ago
Another solution :

By ratio their wages 4 : 3 : 1, totally 8parts

(i.e) 4 + 3 + 1 = 8. athe value of one part = 3200/8 = 400.
C part is one so the answer is 400 rupees.

Vandana said:   7 months ago
Here the ratios of 1/6 : 1/8 : 1/24 do not equal the ratios 4:3:1 as shown in the explanation, there seems to be a mistake in the calculation, it comes to values 3 : 4 : 12.
(14)

BR Alam said:   1 year ago
A can do it in 6 days.
B can in 8 days.
Total work is 24 units (as 24 is the L.C.M of 6 & 8).
A + B + C = 8
(A + B + C) - (A + B),
= 8 - 7,
= 1.

1/8 * 3200 = 400rs.
(24)

Vishal raika said:   10 years ago
C's 1 day work = 1/3-{1/6+1/8} = 1/24.

A:B:C = 1/6*24:1/8*24:1/24*24.

= 4:3:1.

C share = Rs. [Day he worked*Part of work he did*Total share].

= Rs. {3*1/24*3200}.

Venky said:   1 decade ago
No need to calculate wages ratios.

C's part of work for 1 day is 1/24. So the contribution for 3 days is 3/24. As per contribution his share will be 3/24*3200=400.