Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 7 of 19.

RAJNISH JHA said:   10 years ago
Given,
A finish work in 6 days.
B finish work in 8 days.

Then C's 1 day work = 1/3 - (1/6 + 1/8) = 1/24.
Then ratio of a : b : c = 4 : 3 : 1.

Then, C share for 3 days = 3 * 1/24 * 3200 = 400-> answer.

Kumar said:   1 decade ago
The question is actually not clear. Its should say A, B and C undertook the work for Rs.3200. The questions as it is stated may imply that A and B took Rs.3200 individually. Correct me if I'm wrong.

Hemanth said:   1 decade ago
The question is actually not clear. Its should say A, B and C undertook the work for Rs.3200. The questions as it is stated may imply that A and B took Rs.3200 individually. Correct me if im wrong.

Anjana S Babu said:   1 decade ago
A's 1 day work = 1/6.

B's 1 day work = 1/8.

C's 1 day work = 1/3.

We can calculate both A+B = 1/6+1/8.

= 8+6/48 = 14/48.

= 7/24.

Then C's 1 day work = 1/3-7/24.

= 24-21/72 = 3/72.

= 1/24.

Keerthana S said:   2 months ago
See,

I hope everyone gets dout on how 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
So first consider this 1/6:1/8:1/24
LCM will be 24 so, then
1/6 × 24 = 4.
1/8 × 24 = 3.
1/24 × 24 = 1.
So, it's 4 : 3 : 1.
(5)

Prince dubey said:   1 decade ago
Wages ratio is not important short method is.

C work in 3 days.

A & B money = 3200.

C work ratio is 1/24 by method (1/3- (1/6+1/8) ).

Last calculation is 3*1/24*3200.

Answer is 400.

HimiD said:   9 years ago
We see that C can finish it in 3 days. So, C works harder. If we divide Rs 3200 by 3 its Rs 1066.67. As C works harder C should get more than Rs. 1066.67. So, why he is getting Rs. 400?

Kartik said:   1 year ago
The Lcm of 6 and 8 is 24(total work) the A = 4 and B = 3.
Given 3(A+B+C) = 24.
By substituting A and B values C = 1.
The ratios of A, B, C are 4:3:1.
C's share is = 1/8 × 3200 = 400.
(66)

Praveen kumar said:   7 years ago
The sum of three numbers is 275. If the ratio between the fast and second be 3:7 and that between the second and third be 4:5 then find the second number. Can anyone solve this?

Rahul chourasia said:   1 decade ago
Wages ratio is not important short method is
c work in 3 days
a & b money =3200
c work ratio is 1/24 by method (1/3-(1/6+1/8))
last calculation is 3*1/24*3200
ans is 400