A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
184 comments Page 5 of 19.

Reshma said:   6 years ago
Ratio = 4:3:1.
4x3x + x = 3200.
8x = 3200,
X = 400,
C's share = 400.
(1)

Ahin said:   6 days ago
The easiest solution to this question is to find the efficiency of a + b + c - (a + b). You would be getting 1 as c's efficiency.

So, the total work done by a + b + c is 8.
i.e. 1 is divided by 8 * 3200. And You'll get 400.
(1)

Satya Ranjan Sethy said:   4 days ago
Work done by A in one day = 1/6.
Like this of B = 1/8.
The work done by both A and B is 1/6 + 1/8 = 7/24.
3 days work of A and B is 3 * 7/24 = 7/8.

A and B complete 7 parts (for 7/8) of the total work (as we consider the total work is 1),
So, C does 1/8 (which means 1 part of the total work)
So 3200/8 = 400(for each part),
c will be paid 400.
(1)

Sandy said:   2 decades ago
From where did 1/24 come?

Sandy said:   2 decades ago
@Sandy that is c's one day work.. ok.... @dhanush has clearly explained...

Guna said:   2 decades ago
@Vinita

Its simple L.C.M
24-21/24*3=3/72=1/24...

SIDDHARTH said:   2 decades ago
IN 3*1/24*3200...FROM WHERE 3 IS COME

Sahil Kapoor said:   2 decades ago
I agree with siddharth, either the 3 should be removed or they should mention that A,B,C charge Rs 3200 "PER DAY"

Aatif said:   2 decades ago
1/24 is the work done by C in one day. For three days "3" is used.

Jagjeet said:   2 decades ago
I agree in question they should mention 3200 per day.