Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 3 of 18.

Krishna said:   1 decade ago
See jeevana ,

a,b,c can complete work in 3 days
so a,b,c can complete a work in 1 days=1/3...........(1)
a and b can complete work in 1 day=1/6+1/8=7/24works.....(2)

c's one day works =a's and b's one day works is subtracted from a b c one days work that is(1-2)

So 1/24 works done by c
c 's 3 days work is 3/24=1/8
so c's share is = 3200/8=400

Abhishek Giri said:   8 years ago
@ALL.

3 days work.
A completes in 6 days so he should get half of Rs.3200 i.e., 1600.
B's completes in 8 days means half work in 4 days. that means he has worked 1 day less than A
3200/2 = 1600.
1600/4 (B half days work) = Rs. 400 for 1-day work.
so 1600-400 = Rs .1200 (B will get).
Remaining C.
1600+1200 = 2800.
3200-2800 = 400(C will get).

Racha Maheshwari said:   4 years ago
A can complete the work in 6 days means.
A = 3200/6 = 533.33.

B can complete the work in 8 days means.
B = 3200/8 = 400.

Now add A+B=933.3.

All can complete the work in 3days so multiply (A+B) with 3 now the answer is 2799. 899.
Now we can find the C value by substrating 2799.899 with 3200 which is approximately 400 so the value of C is 400.
(19)

Chandana said:   1 decade ago
C's one days work is 1/3.

A and B's one day work is 1/6 and 1/8 respectively.

Now to know the amount of work done by C, we have to calculate the work done by A and B, i.e.,

1/6 + 1/8= 7/24, now we have to calculate how much work C alone has alone done so, 1/3 - 7/24 take LMC you will get 8-7 / 24 you will get 1/24

And now 3*1/2*3200 = 400.

Soumyajit Roy said:   1 decade ago
A's work of 1 day = 1/6 B's work of 1 day = 1/8.

A's work of 3 days = 1/6*3 = 1/2 B's work of 3 days = 1/8*3 = 3/8.

(A+B) 's work of 3 days (1/2 + 3/8) = 7/8.

So the left work in 3 days is done by C.

That is, (1 - 7/8) = 1/8.

Now A, B, C share in the whole money is depend on their work ratio.

So C's Share is 1/8*3200 = 400.

Vinod Anand said:   1 decade ago
If A=1/6 ,B=1/8 and A+B+C = 1/3 ----(1).

A+B = 1/6 + 1/8 = 7/24.

Put the value of A+B in Eq.(1).

Than C = 1/8 - 7/24 = 1/24.

The Value of C' is 1/24.

Now the Ratio of A:B:C =1/6:1/8:1/24 (The L.C.M Of 1/6+1/8+1/24 is 24)
A:B:C =4:3:1.

Than Amt.is Rs.3200.

So the C' will be paid = 3200 X 1/8.

= Rs. 400.00 Answer.

Sai vinay said:   10 years ago
A's work = 1/6.

B's work = 1/8.

A+B+C = 1/3 per day.

C = (A+B+C) - (A+B).

= (1/3) - ((1/6)+(1/8)).

= 1/24.

So A:B:C = 1/6:1/8:1/24.

LCM = 24.

Ratio = 4:3:1.

T.P = (4+3+1) = 8.

8 parts--------------------->3200.

Then C's 1 part---------------------->?

-->8*x = 3200*1.

x = 3200/8.

C money = 400.

Parvatraj said:   1 decade ago
According the quetion,

A can do in 1 day 1/6 work. in 3 days 3/6 work.
B can do in 1 day 1/8 work. in 3 days 3/8 work.
So C has done (1-(3/6+3/8)) work. That is 1/8 work.
So he has to get 1/3 of total amount. i.e, 3200/8=400 rs.

But the calculation they have given is wrong. but answer is right unfortunately.

Pradeep Koney said:   1 decade ago
No need to do all this hard work dudes......

A works 6days and gets 3200,i.e.,for one day=3200/6=1600/3

B works 8days and gets 3200,i.e.,for one day=3200/8=400

A&B&C worked for 3days

That is A gets 3*1600/3 for 3days=1600

B gets 3*400 for 3days=1200

A+B wages=1600+1200=2800

C wages=3200-2800=400
(1)

Ravi said:   4 months ago
A + B + C = 1/3
1/6 + 1/8 + 1/x = 1/3.
(4+3)/24 + 1/x = 1/3.
1/x = 1/3 - 7/24
1/x = (8-7)/24
1/x = 1/24.

Therefore x= 24.
Now 1/6 : 1/8 : 1/24.
4/24 : 3/24 : 1/24,
4 : 3 : 1.
So C share is 1 total share 8
C's share = (3200/8 ) *1,
= 400*1,
= 400.
(16)