Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
184 comments Page 18 of 19.

Aatif said:   2 decades ago
1/24 is the work done by C in one day. For three days "3" is used.

Sahil Kapoor said:   2 decades ago
I agree with siddharth, either the 3 should be removed or they should mention that A,B,C charge Rs 3200 "PER DAY"

SIDDHARTH said:   2 decades ago
IN 3*1/24*3200...FROM WHERE 3 IS COME

Guna said:   2 decades ago
@Vinita

Its simple L.C.M
24-21/24*3=3/72=1/24...

Vinita said:   2 decades ago
Sir pls explain me this step 1/3-7/24= 1/24
How is it?
(1)

Sandy said:   2 decades ago
@Sandy that is c's one day work.. ok.... @dhanush has clearly explained...

Sandy said:   2 decades ago
From where did 1/24 come?

Ravi said:   2 decades ago
The highest among the denominators is 24..so multiply the ratios by 24..
24/6:24/8:24/24
4:3:1
(1)

Harish said:   2 decades ago
1/6:1/8:1/24==4:3:1 how its came give me the logic
(1)

Shyam said:   2 decades ago
It is simple, A's share is (4/8)*3200

B's share is (3/8)*3200

C's share is (1/8)*3200
(1)


Post your comments here: