5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 15 of 18.

Shro said:   1 decade ago
Why to subtract C's work from (A and B) in 1st step?

Vikas said:   1 decade ago
No need to calculate the ratios its just wast of time.

Bev said:   7 years ago
Easier way to work it out.

(3/8+3/6) -1 x 3200 = 400.

Jagjeet said:   1 decade ago
I agree in question they should mention 3200 per day.

Sri said:   1 decade ago
@Pradeep koney.

Thanks Pradeep your method is easy.

Aakash said:   9 years ago
Why we required for ratio of wages in this question?

Harish said:   1 decade ago
1/6:1/8:1/24==4:3:1 how its came give me the logic

Soumya said:   1 decade ago
Can we solve the problem without calculating ratio?

Sweta said:   8 years ago
Can any one help me how the first step is possible?

Nithya said:   9 years ago
Your method is good % easy, Thanks @Pradeep Koney.