Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Answer: Option
Explanation:
| C's 1 day's work = | 1 | - | ![]() |
1 | + | 1 | ![]() |
= | 1 | - | 7 | = | 1 | . |
| 3 | 6 | 8 | 3 | 24 | 24 |
| A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
| 6 | 8 | 24 |
C's share (for 3 days) = Rs. |
![]() |
3 x | 1 | x 3200 | ![]() |
= Rs. 400. |
| 24 |
Discussion:
185 comments Page 14 of 19.
Yash said:
1 decade ago
I didn't understand the step.
How they multiplied wage of C with 3?
How they multiplied wage of C with 3?
Zeenat said:
7 years ago
1/6 * 24 : 1/8 * 24 :1/24 * 24 convert fraction to the whole number.
Reshma said:
6 years ago
Ratio = 4:3:1.
4x3x + x = 3200.
8x = 3200,
X = 400,
C's share = 400.
4x3x + x = 3200.
8x = 3200,
X = 400,
C's share = 400.
(1)
Bhabani said:
1 decade ago
You can directly write there 4x+3x+x=3200, then you also got x=400.
Renju K S said:
1 decade ago
For what purpose we need to find ratio of wages for this question?
DumbAss said:
1 decade ago
Please help.
Where did the number 8 come from in 1/8*3200 = 400?
Where did the number 8 come from in 1/8*3200 = 400?
Prasad said:
1 decade ago
C's share is=[1/(4+3+1)]*3200;
Is it ok to solve by this method
Is it ok to solve by this method
Jeevana said:
1 decade ago
Can anyone help me with the first step?
why do like that only
why do like that only
Pradeep sharma said:
1 decade ago
Thanks a lot Sapna. You have cleared my confusion about 7/24.
Danish said:
1 decade ago
How do you guys know that C's work ratio is 24? Please help.
Post your comments here: