Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 15 of 18.

K appala naidu said:   9 years ago
A's one day work = 1/6
B's one day work= 1/8
C's one day work = 1/x

A + B + C one day work = 1/3.

1/6 + 1/8 + 1/x = 1/3.
C's one day work is 1/24.

The ratio of A : B : C is 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
For 8 parts 3200 for C's 1 part 3200/8 = 400. So, the answer is 400.

Ahamika said:   9 years ago
I still can't understand the solution. Is there any shortcut to find the solution?

Malli said:   9 years ago
How 1/6, 1/8, 1/24 converted into 4 : 3 : 1?

Shyam said:   8 years ago
A bullocks & B tractors can shield a field in 8 days. If we halve the bullocks and double the tractors then it takes 5 days. In how many days A bullocks can shield the field?

Please answer this question.

Bhuvana said:   8 years ago
The LCM of 6,8 and 24.Then,

24/6 = 4
24/8 = 3
24/24 = 1.

So, that the ratio becomes 4:3:1.

Shri said:   8 years ago
It forms equation. Just simplify you'll get answer @Shyam.

HimiD said:   8 years ago
We see that C can finish it in 3 days. So, C works harder. If we divide Rs 3200 by 3 its Rs 1066.67. As C works harder C should get more than Rs. 1066.67. So, why he is getting Rs. 400?

SAI SRI said:   8 years ago
A's SHARE =3/6*3200 = 1600.
B's SHARE =3/8*3200 = 1200.

TOTAL A & B =1600+1200 = 2800.
C's SHARE =3200-2800 = 400.

Abhishek Giri said:   8 years ago
@ALL.

3 days work.
A completes in 6 days so he should get half of Rs.3200 i.e., 1600.
B's completes in 8 days means half work in 4 days. that means he has worked 1 day less than A
3200/2 = 1600.
1600/4 (B half days work) = Rs. 400 for 1-day work.
so 1600-400 = Rs .1200 (B will get).
Remaining C.
1600+1200 = 2800.
3200-2800 = 400(C will get).

Kartik Choudhary said:   8 years ago
Please make me understand this.

We calculated ratio 4:3:1.
But how's the last step is done?
How we calculated C's share. Please elaborate it.