Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
186 comments Page 15 of 19.

Ankit said:   1 decade ago
A finish work in day = 6,

B finish work in day = 8,

LCM = 24.

A doing work in one day = 24/6 = 4,

B doing work in one day = 24/8 = 3,

If both are work together, so one day work = 4 + 3 = 7.

So, one day work = 7/24,

In three day = 3(7/24),

A and B combined rupee = 21/24*3200 = 2800.

So, C = 3200 - 2800 = 400.

Please suggest me, this is true or wrong.

RAJNISH JHA said:   1 decade ago
Given,
A finish work in 6 days.
B finish work in 8 days.

Then C's 1 day work = 1/3 - (1/6 + 1/8) = 1/24.
Then ratio of a : b : c = 4 : 3 : 1.

Then, C share for 3 days = 3 * 1/24 * 3200 = 400-> answer.

Naveen said:   1 decade ago
@Pradeep, your method is really superb and very easy to understand. Thank you so much.

Vasanth said:   1 decade ago
Another solution :

By ratio their wages 4 : 3 : 1, totally 8parts

(i.e) 4 + 3 + 1 = 8. athe value of one part = 3200/8 = 400.
C part is one so the answer is 400 rupees.

Nithya said:   1 decade ago
Your method is good % easy, Thanks @Pradeep Koney.

Bharath said:   10 years ago
NO need of looking for ratios. Just understand the question and do logically.

A = 6days
B = 8days
C = ?
A + B + C = 3200rupees.

Now we need to find how many days would C take to complete his work.
1/6 + 1/8+ C = 1/3.
C = 1/3 - (1/6 + 1/8).
1/3 - (7/24).
1/24.

So, here we found that C can do 1/24 work in one day, now in 3 days C can do:
3 * 1/24 = 1/8.

Now 1/8 * 3200 gives us the answer.
So, 1/8 * 3200 = 400.

Ashish said:   10 years ago
We can also use the lcm method.

K appala naidu said:   10 years ago
A's one day work = 1/6
B's one day work= 1/8
C's one day work = 1/x

A + B + C one day work = 1/3.

1/6 + 1/8 + 1/x = 1/3.
C's one day work is 1/24.

The ratio of A : B : C is 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
For 8 parts 3200 for C's 1 part 3200/8 = 400. So, the answer is 400.

Ahamika said:   10 years ago
I still can't understand the solution. Is there any shortcut to find the solution?

Malli said:   10 years ago
How 1/6, 1/8, 1/24 converted into 4 : 3 : 1?


Post your comments here:

Your comments will be displayed after verification.