Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 30)
30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
Answer: Option
Explanation:
Let A's 1 day's work = x and B's 1 day's work = y.
Then, x + y = | 1 | and 16x + 44y = 1. |
30 |
Solving these two equations, we get: x = | 1 | and y = | 1 |
60 | 60 |
![]() |
1 | . |
60 |
Hence, B alone shall finish the whole work in 60 days.
Discussion:
97 comments Page 3 of 10.
Sushma said:
1 decade ago
Hi all
Can any one explain clearly above 1, that hw the answer would be x=1/60 & y=1/60............
I think we cant get it from abve eqns that 16x +44y=1
x+y=1/30
Can any one explain clearly above 1, that hw the answer would be x=1/60 & y=1/60............
I think we cant get it from abve eqns that 16x +44y=1
x+y=1/30
Shraddha said:
1 decade ago
Multiply x+y=1/30 by 16 and that gives 16x+16y=8/15
subtract 16x + 16y = 8/15
-
16x + 44y =1
----------------
28y = 7/15
hence, y=1/60
substitute y= 1/60 in x+y=1/30 and we get, x=1/60
subtract 16x + 16y = 8/15
-
16x + 44y =1
----------------
28y = 7/15
hence, y=1/60
substitute y= 1/60 in x+y=1/30 and we get, x=1/60
Shraddha said:
1 decade ago
A's 16 days work + B's 44 days work = 1
(A+B) 16 days work + B's 28 days work = 1
but (A+B) 1 days work= 1/30
hence, (A+B) 16 days work = 8/15
therefore,
8/15 + B's 28 days work = 1
B's 28 days work = 1- 8/15
= 7/15
B's 1 days work = 1/60
(A+B) 16 days work + B's 28 days work = 1
but (A+B) 1 days work= 1/30
hence, (A+B) 16 days work = 8/15
therefore,
8/15 + B's 28 days work = 1
B's 28 days work = 1- 8/15
= 7/15
B's 1 days work = 1/60
Avi said:
1 decade ago
For completion of one work it took A, B for 30 days.
So let A's one day work is x & B's one day work is y.
From above we can write 1 work=30x+30y.
But in second case a worked for 16 days & B worked for 44days.
Therefore,
16x+44y=1 work.
By solving we can get y=1/60 work.
So let A's one day work is x & B's one day work is y.
From above we can write 1 work=30x+30y.
But in second case a worked for 16 days & B worked for 44days.
Therefore,
16x+44y=1 work.
By solving we can get y=1/60 work.
Abhilash said:
1 decade ago
How to solve alternative working days problem in time and work?
Dhiraj said:
1 decade ago
Another way:
A + B = 60.
So A and B's together 1 day's work =1/60.
A's 1 day work = 1/16.
B's 1 day work = 1/44.
A works 16 days and leaves so int that A+B = 1/60, multiply A's work out of 60 days, Which gives number of work A has done.
Therefore 16/60=4/15 = A's work with B in 60 days.
Remaining work for 1 day = 1-4/15 = 11/15.
In those Remaining work has to Be done by B as he has to finish the work alone - 15/11*44 = 60 Days. This is Easy way.
A + B = 60.
So A and B's together 1 day's work =1/60.
A's 1 day work = 1/16.
B's 1 day work = 1/44.
A works 16 days and leaves so int that A+B = 1/60, multiply A's work out of 60 days, Which gives number of work A has done.
Therefore 16/60=4/15 = A's work with B in 60 days.
Remaining work for 1 day = 1-4/15 = 11/15.
In those Remaining work has to Be done by B as he has to finish the work alone - 15/11*44 = 60 Days. This is Easy way.
Harish said:
1 decade ago
I don't think we should bother about 30 days' combined work. That piece of problem is, I think, meant to confuse us. Because he wishes to know B's individual capacity of doing what is left out by A's individual work.
Whatever A leaves behind, B finishes it.
Hence it is as simple as 16+44 = 60 days.
Whatever A leaves behind, B finishes it.
Hence it is as simple as 16+44 = 60 days.
Sai said:
1 decade ago
If 8/15 of the work is done by A in 16 days, then remaining 7/15 of the work is done by B in 44 days right....then why not cross multiply for 15/15 of the work.
I am getting a wrong answer doing this. Can anyone explain please.
7/15 work ----- 44 days.
15/15 work ----- k days.
k = 44*15/7 = 94.28.
I am getting a wrong answer doing this. Can anyone explain please.
7/15 work ----- 44 days.
15/15 work ----- k days.
k = 44*15/7 = 94.28.
Achesh said:
1 decade ago
This answer can still be solved by only having the basic formulas in mind.
Let A take x and B take y days to complete the whole work.
From question, we know,
1/x+1/y = 30 . By solving this we get,
xy = 30x+30y ... (1).
Now, work done by A in 1 day is 1/x. Therefore in 16 days = 16/x.
Remaining work = 1-(16/x).
This remaining work is done by B in 44 days.
And we have assumed that B takes y days to complete the job.
So for B.
WORK : Days
1 : y
1-(16/x) : 44
Solving this equation we get,
xy = 44x+16y ... (2).
Comparing (1) and (2),
30x+30y = 44x+16y.
Solve this and we get x=y.!
Put this in first equation , i.e.
1/y+1/y = 1/30.
2/y = 30.
Therefore, y = 60!
Hence 60 days.
Lengthy, but easy and precise :).
Let A take x and B take y days to complete the whole work.
From question, we know,
1/x+1/y = 30 . By solving this we get,
xy = 30x+30y ... (1).
Now, work done by A in 1 day is 1/x. Therefore in 16 days = 16/x.
Remaining work = 1-(16/x).
This remaining work is done by B in 44 days.
And we have assumed that B takes y days to complete the job.
So for B.
WORK : Days
1 : y
1-(16/x) : 44
Solving this equation we get,
xy = 44x+16y ... (2).
Comparing (1) and (2),
30x+30y = 44x+16y.
Solve this and we get x=y.!
Put this in first equation , i.e.
1/y+1/y = 1/30.
2/y = 30.
Therefore, y = 60!
Hence 60 days.
Lengthy, but easy and precise :).
Kaustubha Sen said:
1 decade ago
I think there is a mistake in the understanding.
"A having worked for 16 days, B finishes the remaining work alone in 44 days"
Look at this line.
- A worked for 16 days
- B finishes remaining work "ALONE" in 44 days.
So, it is never mentioned that A worked 16 days alone. I think it should be interpreted as - A worked with B for 16 days and then stopped. B did the remaining in 44 days.
Thus Solution is -
Let A's 1 day's work = x and B's 1 day's work = y
Then, x + y = 1/30 and 16*(x + y) + 44y = 1
Solving we get,
16 * (x + y) + 44y = 1.
or 16 * 1/30 + 44y = 1.
or 44y = 1 - 16/30.
or y = (14/30)/44.
Thus B finishes the work in (44 * 30)/14 = 94.285714.
"A having worked for 16 days, B finishes the remaining work alone in 44 days"
Look at this line.
- A worked for 16 days
- B finishes remaining work "ALONE" in 44 days.
So, it is never mentioned that A worked 16 days alone. I think it should be interpreted as - A worked with B for 16 days and then stopped. B did the remaining in 44 days.
Thus Solution is -
Let A's 1 day's work = x and B's 1 day's work = y
Then, x + y = 1/30 and 16*(x + y) + 44y = 1
Solving we get,
16 * (x + y) + 44y = 1.
or 16 * 1/30 + 44y = 1.
or 44y = 1 - 16/30.
or y = (14/30)/44.
Thus B finishes the work in (44 * 30)/14 = 94.285714.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers