30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
Answer: Option
Explanation:
Let A's 1 day's work = x and B's 1 day's work = y.
Then, x + y = | 1 | and 16x + 44y = 1. |
30 |
Solving these two equations, we get: x = | 1 | and y = | 1 |
60 | 60 |
![]() |
1 | . |
60 |
Hence, B alone shall finish the whole work in 60 days.
Discussion:
97 comments Page 10 of 10.
Md Liton gazi. said:
3 years ago
A worked 16 days.
If 16 days= x portion.
The remaining work is 1-x portion.
which portion B finished by 44 days.
Then,
1-x = 44,
1-16 = 44 (x=16),
1 = 44 + 16,
1 = 60 (1= total portion)
Am I right? Please tell me.
If 16 days= x portion.
The remaining work is 1-x portion.
which portion B finished by 44 days.
Then,
1-x = 44,
1-16 = 44 (x=16),
1 = 44 + 16,
1 = 60 (1= total portion)
Am I right? Please tell me.
(16)
Abir said:
3 years ago
30A + 30B = 16A + 44B.
A:B = 1 : 1.
Capability of both are equal,
A+B = 30,
2person need = 30days.
1person need = 2 * 30 = 60days.
A:B = 1 : 1.
Capability of both are equal,
A+B = 30,
2person need = 30days.
1person need = 2 * 30 = 60days.
(67)
Chandana Hazarika said:
3 years ago
A+B's 1days work = 1/30
A+B's 16days work = 1/30*16=8/15
Now,
B's 1day work =8/15-1/30=1/2
So, B's 16day work will be=1/2*16=8.
*Now we have to find out the remaining work*
Remaining work =(1-8/15)=7/15.
ATQ,
B does the remaining work,e.i 7/15 portion work in =44 days.
And 8 portions work in 16 days.
Therefore B shall finish the whole work alone in =(44days + 16days) = 60 days.
A+B's 16days work = 1/30*16=8/15
Now,
B's 1day work =8/15-1/30=1/2
So, B's 16day work will be=1/2*16=8.
*Now we have to find out the remaining work*
Remaining work =(1-8/15)=7/15.
ATQ,
B does the remaining work,e.i 7/15 portion work in =44 days.
And 8 portions work in 16 days.
Therefore B shall finish the whole work alone in =(44days + 16days) = 60 days.
(11)
Aakash said:
3 years ago
90 days is the right answer.
(6)
Laxmikatnt Kulkarni said:
3 years ago
60 days is the right answer!
(5)
Abhilasha Varshney said:
2 years ago
Let's take A to complete a work in x days and B to complete a work in Y days.
A's 1 day work =1/x and B's 1 day work =1/Y.
A and B together complete a work in 30 days so 1/X +1/Y = 1/30.
A's 16 days of work = 16/X
Remaining work = 1-16/X = X-16/X.
B completes the remaining work in 44 days so X-16/X work will be completed by B in 44 days
B will complete the whole work in 44X/X-16 days which would be equal to Y (because B completed a work in Y days)
So, Y = 44X/X-16.
since 1/X+1/Y = 1/30.
so, 1/X+X-16/44X = 1/30,
44+X-16/44X = 1/30,
X+28/44X = 1/30,
30X+840 = 44X,
14X = 840,
X = 60 days.
A's 1 day work =1/x and B's 1 day work =1/Y.
A and B together complete a work in 30 days so 1/X +1/Y = 1/30.
A's 16 days of work = 16/X
Remaining work = 1-16/X = X-16/X.
B completes the remaining work in 44 days so X-16/X work will be completed by B in 44 days
B will complete the whole work in 44X/X-16 days which would be equal to Y (because B completed a work in Y days)
So, Y = 44X/X-16.
since 1/X+1/Y = 1/30.
so, 1/X+X-16/44X = 1/30,
44+X-16/44X = 1/30,
X+28/44X = 1/30,
30X+840 = 44X,
14X = 840,
X = 60 days.
(2)
Ugyen JIgme Chogyel said:
5 months ago
Then, In how many days shall B finish the whole work alone?
Anyone, please answer this.
Anyone, please answer this.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers