Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
283 comments Page 8 of 29.

Jezan said:   1 decade ago
According to this question if A is x, B will be x+60
1/3=x/x+60
3x=x+60
2x=6
x=30
A+B'S ONE DAY WORK=1/30+1/90=2/45
SO WHOLE WORK S= 45/2( UPSIDE DOWN)
22.5 DAYS.
HOPE ALL LL GET DIS

Jaswinder Singh said:   1 decade ago
Ratio of times taken by A and B = 1 : 3. or 1x:3x
so, we say
3x-1x=60,
2x=60,
x=30, so A will 30 day to complected a work,
B will be complete the work ie 3x, 3(30)=90days,
(A+B) 1 Day work = (1/30 + 1/90)
by solving we get,
A+B 1 Day work = 2/45,
so A and B together can complete work in 45/2 Days.

Sharan said:   1 decade ago
@Jaswinder singh: I understood your explanation man. Thanks.

Deepti said:   1 decade ago
It is not so big and easy to understand.

let work done by B in 1 day = 1/x
so work done by A in 1 day = 1/(x-60)
1/(x-60) = 3/x
so x = 3x - 180
x = 90
work done by A and B in 1 day is 30 and 90 respectively
work done by both together in 1 day = 1/30 + 1/90 = 2/45.
total work done = 45/2

Harsha said:   1 decade ago
Easy method :

A can completed in x days
B can in 3x days then

A = B-60 (A can do in 60 days less than B )

=> x=3x-60 => x= 30 =>

A=30, B=90

Then together work done is (1/30+1/90) = 2/45.

Finally total work done is 45/2.

Pinky said:   1 decade ago
@Sheetal superb explanation.

Praveen said:   1 decade ago
Nice exp. Harsha.

Nitin Singla said:   1 decade ago
Hey its simple to understand.
Days taken by B = x
Days taken by A= x - 60
Their time taken proportio is 1:3
so,
x - 60/ x = 1/3
x=90;
So A will do the work in = 30 days
abd B in 3x= 3*30=90 days,
and u can find their 1 day's work and ad it.
Simple :)

Srinivas said:   1 decade ago
Hi friends,

Given A:B=1:3

Therefore B=3A--------equation 1

let B can do a work in x days.

then A can do the same work in (x-60) days.

then B=3A
x=(x-60)3

therefore x=90 days

therefore B can do a work in 90 days.

and A will do a work in 90-60=30 days.

Pavethra said:   1 decade ago
I tell that A is thrice as good as B so it should be 3:1 na.

Am I right?


Post your comments here:

Your comments will be displayed after verification.