Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 23 of 29.

Nik said:   8 years ago
How 4/90 comes?

Rizwan said:   8 years ago
From where does this 4/90 comes? How 4?

Vishal said:   8 years ago
I have better solution.

A:B-3:1(rate).
A:B-1:3(days).

Diff of 2 between ratio of days which is equivalent to 60 and 2*30=60.
Hence 30 will be multiplied to 1 and 3.
And we get 30 and 90.
Together days taken= 30 * 90/30 + 90 = 22 1/2.

Dusu opo said:   8 years ago
Why 60 days? Please explain.

Sherin said:   8 years ago
Thank you @Showry.

Jiban said:   8 years ago
Can it be in this way?

B will take 180 days more than A. Then calculate for 1 day.

Can anyone solve this?

Nurun Nobi Khokon said:   7 years ago
Let A take x days
So, B takes x+60 days

3x = x+60 (B took 3 times more, so to make the equation equal he have to multiply the days taken by A by 3).
or, 2x = 60,
or, x = 30 days.

A takes 30 days and b takes 30+60 or 90 days.,
Now, (A+B)'s 1 day's work = (1/30+1/90) or 4/90 or 2/45,
So, total days required to do the whole work, 45/2 or 22.5 days.

Kavitalodhi said:   7 years ago
In the question clearly, say that A takes 60 days less than B.

So A can do the work in B-60 days,
And time ratio of A:B = 1:3,
1/3=B-x/B =>B=90,A=30.

So, A and B can do the work together 1/30+1/90 =>2/45,
Mix fraction of 2/45 is 22 1/2.

Mohit said:   7 years ago
3 x 60/3^2-1 = 22 1/2.

Balaji said:   7 years ago
Capacities of A:B=3:1.
Time taken ratio of A:B=1:3.
Difference of ratio in time is 2 = 60 days => A takes 30 days and B takes 90 days => 90/4=22 1/2.