Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 20 of 29.

Dineshkumar said:   9 years ago
Your answer is clear @Sundar, Thanks.

Hari said:   9 years ago
A:B = 3:1 efficiency.
Because, A is Thrice the work as B.
So, A complete the work 60 days before.
Then 2---60
1--30,

So to find total work we just take it as;
A = 3 * 30. B = 1 * 30.

Total work is 90(LCM IS 90).
So, W = ED,
D = 90/4
= 22.5.

BLACK said:   9 years ago
Ratio of time taken by A & B = 1 : 3.
Suppose B takes x days to finish the job.
Then A takes (x-60) days.
So, (x-60) : x = 1:3
x= 90.
So rest are same.

@verma ji said:   9 years ago
Hello Friends: this shortcut formula is better to solve these type question in less time.

Alternate Method: Since 'A' is 'm' times as efficient as 'B' & takes 'D' days less than 'B', then the time required to complete the job together is given by,

T = m * D/(m^2 " 1)

T = 3 * 60 / [(3)^2 - 1] = 180 / 8 = 22 1/2 days.

Suresh said:   8 years ago
A is 3 times more efficient than B,
A=3B
A do the work less than 60 days compared to B,
A-60=B.

So, we can write it as,
A = 3(A+60)
A = 3A+180
2A = 180
A = 90
90-60 = B
B = 30.

Hari. said:   8 years ago
Thanks @Sachin.

JAY said:   8 years ago
LET:
A = 3B.
where:
A = 1/x and B = 1/(x+60)
so;
(1/x) = 3[ 1/(x+60) ]
X = 30.

1/A + 1/B = 1/T
1/30 + 1/(30+60) = 1/T
Then, T = 22.5 answer.

JPV said:   8 years ago
Ratio of no days taken to do work by and b= x : 3x.

It's give that diff= 60.

ie 3x-x = 60,
ie x = 30.

No of days taken by B=90.
No of days taken by A=30.

ie total no of days taken when work is done together= 1/30 +1/60,
= 22 1/2.

Sahil Husain said:   8 years ago
A=3B ----------(1)
A-60=B----------(2) from equation 1 & 2

3B-60 = B
B=30 and A = 90
(A+B)'S 1 day work =1\90+1\30 = 2\45,
So (A+B)'s work = 45\2 = 22 1\2.

Dipak said:   8 years ago
Guys. I'm giving simple approach.

3x - x = 60
x = 30
So respective days are 90 and 30.
Total days together = 30 * 90/120 = 22.5.