A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
Discussion:
287 comments Page 19 of 29.
Yash Sangle said:
9 months ago
3/1 = (B)/(B-60).
As work done and time are inversely related,
so, B = 90, A = 30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
As work done and time are inversely related,
so, B = 90, A = 30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
(13)
Satyawan said:
1 decade ago
The explanation given above is very difficult to understand please try to explain the concepts as simple as possible.
Insane said:
10 years ago
Let A be X where as b = 3x.
So,
3x - x = 60.
x = 30.
a = 30, b = 90.
Together they can do the work in 22 (1/2) days.
So,
3x - x = 60.
x = 30.
a = 30, b = 90.
Together they can do the work in 22 (1/2) days.
Ankush Rana said:
1 decade ago
A is twice as good as workman B and together they finish a piece of work in 14 days. A alone can finish the work in.
Priti said:
6 years ago
***shortcut method******
D= no of days.
n= n times as fast.
D*n/n^2-1
60*3/3^2-1
180/9-1
180/8=90/4=22 1/2.
D= no of days.
n= n times as fast.
D*n/n^2-1
60*3/3^2-1
180/9-1
180/8=90/4=22 1/2.
Yash Sangle said:
9 months ago
3/1 = (B)/(B-60).
As work done and time are inversely related,
So, B=90, A=30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
As work done and time are inversely related,
So, B=90, A=30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
(5)
Abhay said:
1 decade ago
@Neeraj-A will finish the work 60 days lesser than B,means if B takes 60 days to complete the work,A takes 1 day.
Nikita raisadhar said:
1 year ago
3x - x=60
2x = 60
x = 30
B = 3x = 3 x 30 = 90.
A+B = 1/30 + 1/90,
= 3 + 1/90,
= 4/90,
= 2/42,
= 45/2,
= 22 1/2.
2x = 60
x = 30
B = 3x = 3 x 30 = 90.
A+B = 1/30 + 1/90,
= 3 + 1/90,
= 4/90,
= 2/42,
= 45/2,
= 22 1/2.
(74)
Nallapu Rishith Reddy said:
9 months ago
3/1 = (B)/(B-60).
As work done and time are inversely related,
so, B=90, A=30.
(1/90+1/30)=(2/45),
So, 22 1/5.
As work done and time are inversely related,
so, B=90, A=30.
(1/90+1/30)=(2/45),
So, 22 1/5.
(5)
Jiban said:
8 years ago
Can it be in this way?
B will take 180 days more than A. Then calculate for 1 day.
Can anyone solve this?
B will take 180 days more than A. Then calculate for 1 day.
Can anyone solve this?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers


A and B together can do the work in