Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3

Then, 1 + 2 + 3 = 1
x x x 2

6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

Discussion:
68 comments Page 4 of 7.

Rohini said:   1 decade ago
a=2b or a=3c.

=>b=a/2 , c=a/3.
Let us assume a=x.

Then,
a b c
x x/2 x/3

Therefore., (1/x + 2/x + 3/x) = 1/2.
6/x = 1/2.
x = 12.
B alone = x/2 = 12/2 = 6.

Kaviya said:   1 decade ago
How to comes the 1/x+2/x+3/x?

Wangchuk Drukpa said:   1 decade ago
Let C takes x days to complete the work, then:

A, B, C.

3x, 3/2 x and x.

Their respective 1 day's work.

1/3x, 3/2x, 1/x now this is equal to 1/2 (as A+B+C takes 2 days to complete the work, thus their 1 day's work would be half).

Then we get x=4. Now 3/2 of 4 is 6.

Khushwinder pal said:   1 decade ago
Another method.

Suppose C = X.

C = 2X then B = 3X, A = 6X.

Then B = 2X = 2*3 = 6 days.

If asked A = 6*3 = 18 days.

Vidivelli said:   1 decade ago
Let us consider the time taken by B is 2x.

So the time taken by A is "twice of B" then A=4x.

Similarly if time taken by B is x/2, the time taken by A is (2*x/2) = x; the time taken by C is x/3.

So the time taken by A is thrice of C (3* x/3). Hence we get x+x/2+x/3.

Since we consider work for one day we take inverse 1/x+2/x+3/x = 1/2.

G JOGI RAO said:   10 years ago
Hi @Kiran.

If 6A = 2 then A = 3.

But you said it A = 12 give proper explanation?

Dipika said:   10 years ago
If C takes x days to complete a work A will take 3x days.

If B takes y days to complete a work A will take 2y days.

But 3x = 2y, so x = 2/3y.

As per ques, 1/2y+y+2/3y = 1/2.

Therefore y = 6.

B takes 6 days to complete the work.

Naseem Ahmad Saifi said:   10 years ago
As per given:

2A = B => A = B/2......(1).

3A = C......(2).

=> 3*B/2 = C......(2) (from 1st A = B/2).

(A+B+C)'s do the work in 2 days.

So (A+B+C)'s 1 day work is = 1/2.

Put the value of A and C from 1st and 2nd.

= (B/2+B+3*B/2) 's 1 day work = 1/2.

=> 6B/2, 1 day work = 1/2.

=> B's 1 day work = 1/2*2/6 = 1/6.

So B complete work in 6 days.

Punitsw said:   10 years ago
In simple words:

A:B:C = 1:2:3 (Total 6 equivalent to A).

Now A, B and C together complete work in 2 days (i.e in 12 man days of A). So if A, B or C do the work alone, the required days would be:

A = 12 days.
B = 6 days.
C = 4 days.

MONA said:   9 years ago
In simple way:

A =2B , A = 3C,So ratio will be = A : B : C = 1 : 2 : 3.
A = 1 unit/day
B = 2unit/day
C = 3unit/day

A + B + C = 6unit/day.

We don't know the total work in units.
So,
A + B + C = 2 Days
TOTAL WORK/DAYS = 6.
TOTAL WORK = 6 * 2 = 12 UNITS.

So,B = 12/2 = 6 Days.


Post your comments here:

Your comments will be displayed after verification.