Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Answer: Option
Explanation:
Suppose A, B and C take x, | x | and | x | days respectively to finish the work. |
2 | 3 |
Then, | ![]() |
1 | + | 2 | + | 3 | ![]() |
= | 1 |
x | x | x | 2 |
![]() |
6 | = | 1 |
x | 2 |
x = 12.
So, B takes (12/2) = 6 days to finish the work.
Discussion:
68 comments Page 3 of 7.
Mann prajapati said:
1 decade ago
Suppose C can complete work in 18 days then A and B can complete the work in 54 and 27 days respectively.
Now A's 1 day work is 1/54 and B's 1 day work is 1/27 and C's 1/18.
Together 1/54+1/27+1/18=1/9.
Work finishes by together in 9 days.
Now when work complete in 9 days B's days are 27 so when work complete in 2 days B's days=?
27*2/9=6 days.
Now A's 1 day work is 1/54 and B's 1 day work is 1/27 and C's 1/18.
Together 1/54+1/27+1/18=1/9.
Work finishes by together in 9 days.
Now when work complete in 9 days B's days are 27 so when work complete in 2 days B's days=?
27*2/9=6 days.
Mariam said:
1 decade ago
Hai guys, i think mini is correct. from the question we get if B works for 1 hr, A takes 2 hrs to complete the same work i.e.,2A=B
Mahesh Sarangapani said:
1 decade ago
Suppose A, B and C take x, x/2, x/3 days respectively to finish the work.
work done per day by
A is 1/x
B is 1/(x/2)=2/x
C ix 1/(x/3)=3/x
And the work done by A, B and C together per day is 1/2 (since work is completed in 2 days)
So 1/x + 2/x + 3/x = 1/2
6/x = 1/2
x = 12.
Answer : 6
work done per day by
A is 1/x
B is 1/(x/2)=2/x
C ix 1/(x/3)=3/x
And the work done by A, B and C together per day is 1/2 (since work is completed in 2 days)
So 1/x + 2/x + 3/x = 1/2
6/x = 1/2
x = 12.
Answer : 6
FAITH said:
1 decade ago
My thoughts:
Let the time for A to do the job be X.
Let the time for B to do the job be 2X (since A takes twice as much time as B).
Let the time for B to do the job be 3X (since A takes thrice as much time as C).
So it takes all three X+2X+3X = 1/2 (days to finish the job).
This gives 6x=1/2. Therefore x=3.
Therefore the time taken for B to do the work is 2X.
Which is 2*3=6 which is equal to 6days.
It takes 3X that is 3*3 for C to do the work.
Which is equal 9 days.
With the above, you would find out that indeed A takes twice as much time as B and thrice as much time as C.
I hope this would suffice.
Let the time for A to do the job be X.
Let the time for B to do the job be 2X (since A takes twice as much time as B).
Let the time for B to do the job be 3X (since A takes thrice as much time as C).
So it takes all three X+2X+3X = 1/2 (days to finish the job).
This gives 6x=1/2. Therefore x=3.
Therefore the time taken for B to do the work is 2X.
Which is 2*3=6 which is equal to 6days.
It takes 3X that is 3*3 for C to do the work.
Which is equal 9 days.
With the above, you would find out that indeed A takes twice as much time as B and thrice as much time as C.
I hope this would suffice.
KOTHA SRAVANI said:
1 decade ago
Hai friends,
Taking the values of A,B,C as x, x/2, x/3.
1/x + 2/x + 3/x = 1/2.
On calculating we get,
6/x = 1/2.
Therefore, x = 12;
On substituting X = 12 in main equation.
1/12 + 2/12+ 3/12 = 1/2.
Hence, the value of B = 1/6.
Taking the values of A,B,C as x, x/2, x/3.
1/x + 2/x + 3/x = 1/2.
On calculating we get,
6/x = 1/2.
Therefore, x = 12;
On substituting X = 12 in main equation.
1/12 + 2/12+ 3/12 = 1/2.
Hence, the value of B = 1/6.
Ravi said:
1 decade ago
Can anyone please explain me that how these x, x/2, x/3 become 1/x + 2/x + 3/x.
Here I don't get is we take 1 day's work of A as 1/x and after that it's taken 2/x + 3/x as B and C's 1 day work but actually after A's 1 day work B's & C's work should be taken as 1/x/2 and 1/x/3.
Which becomes x/2 and x/3 So finally it should look like 1/x + x/2 + x/3.
Here I don't get is we take 1 day's work of A as 1/x and after that it's taken 2/x + 3/x as B and C's 1 day work but actually after A's 1 day work B's & C's work should be taken as 1/x/2 and 1/x/3.
Which becomes x/2 and x/3 So finally it should look like 1/x + x/2 + x/3.
Apeksha said:
1 decade ago
Why 12 is divided by 2 in last?
Krishman Varges said:
1 decade ago
This can be solved using physics. Force=Power/time. A, B and C does the same amount of work, hence, force is a constant. The power of three differs. Hence 1/t=f/p where f is a constant and t=2. 1/2=1/x+2/x+3/x.
Brijesh said:
1 decade ago
Lets assume that A completes the work in 'x' days.
B completes the same amount of work in 'x/2' days because A takes twice the time than B.
C completes the same amount of work in 'x/3' days because A takes thrice the time than C.
Now the work completed by A in one day is '1/x'.
Work completed by B in one day is '2/x'
Work completed by C in one day is '3/x'
All three together can complete the work in '2' days as given in the problem. So the work done by all three together in one day is '1/2'.
Hence the equation: '(1/x + 2/x + 3/x) = 1/2'.
Evaluating the above equation gives the value 'x=12' which is the number of days taken by A to complete the work.
As we know that number of days taken by B complete the work is 'x/2', we substitute the 'x' value.
Hence the evaluation '12/2' where 12 is the value of 'x'.
HENCE THE TIME REQUIRED BY B TO COMPLETE THE WORK IS 6 DAYS.
B completes the same amount of work in 'x/2' days because A takes twice the time than B.
C completes the same amount of work in 'x/3' days because A takes thrice the time than C.
Now the work completed by A in one day is '1/x'.
Work completed by B in one day is '2/x'
Work completed by C in one day is '3/x'
All three together can complete the work in '2' days as given in the problem. So the work done by all three together in one day is '1/2'.
Hence the equation: '(1/x + 2/x + 3/x) = 1/2'.
Evaluating the above equation gives the value 'x=12' which is the number of days taken by A to complete the work.
As we know that number of days taken by B complete the work is 'x/2', we substitute the 'x' value.
Hence the evaluation '12/2' where 12 is the value of 'x'.
HENCE THE TIME REQUIRED BY B TO COMPLETE THE WORK IS 6 DAYS.
Subhas said:
1 decade ago
A can complete 1 unit/day.
B can complete 2 unit/day.
C can complete 3 unit/day.
Total works complete together by all in 1 days = 6 unit/day.
So, they complete in two days = 6X2 = 12 units.
So B takes 12/2 = 6 days to complete.
B can complete 2 unit/day.
C can complete 3 unit/day.
Total works complete together by all in 1 days = 6 unit/day.
So, they complete in two days = 6X2 = 12 units.
So B takes 12/2 = 6 days to complete.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers