Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Answer: Option
Explanation:
| Suppose A, B and C take x, | x | and | x | days respectively to finish the work. |
| 2 | 3 |
| Then, | ![]() |
1 | + | 2 | + | 3 | ![]() |
= | 1 |
| x | x | x | 2 |
|
6 | = | 1 |
| x | 2 |
x = 12.
So, B takes (12/2) = 6 days to finish the work.
Discussion:
68 comments Page 2 of 7.
Raj said:
9 years ago
2A = B.......eqn1.
3A = C.......eqn2.
A + B + C = 2days
A + 2A + C = 2days (from the eqn1),
A + 2A + 3A = 2days(from the run2),
6A = 2days ,
A = 2/6,
A = 1/3 days.
i.e A takes 3days to work.
We have B=2A.
B=2(3),
B=6.
That's B takes 6 days to complete.
3A = C.......eqn2.
A + B + C = 2days
A + 2A + C = 2days (from the eqn1),
A + 2A + 3A = 2days(from the run2),
6A = 2days ,
A = 2/6,
A = 1/3 days.
i.e A takes 3days to work.
We have B=2A.
B=2(3),
B=6.
That's B takes 6 days to complete.
(1)
Brijesh said:
1 decade ago
Lets assume that A completes the work in 'x' days.
B completes the same amount of work in 'x/2' days because A takes twice the time than B.
C completes the same amount of work in 'x/3' days because A takes thrice the time than C.
Now the work completed by A in one day is '1/x'.
Work completed by B in one day is '2/x'
Work completed by C in one day is '3/x'
All three together can complete the work in '2' days as given in the problem. So the work done by all three together in one day is '1/2'.
Hence the equation: '(1/x + 2/x + 3/x) = 1/2'.
Evaluating the above equation gives the value 'x=12' which is the number of days taken by A to complete the work.
As we know that number of days taken by B complete the work is 'x/2', we substitute the 'x' value.
Hence the evaluation '12/2' where 12 is the value of 'x'.
HENCE THE TIME REQUIRED BY B TO COMPLETE THE WORK IS 6 DAYS.
B completes the same amount of work in 'x/2' days because A takes twice the time than B.
C completes the same amount of work in 'x/3' days because A takes thrice the time than C.
Now the work completed by A in one day is '1/x'.
Work completed by B in one day is '2/x'
Work completed by C in one day is '3/x'
All three together can complete the work in '2' days as given in the problem. So the work done by all three together in one day is '1/2'.
Hence the equation: '(1/x + 2/x + 3/x) = 1/2'.
Evaluating the above equation gives the value 'x=12' which is the number of days taken by A to complete the work.
As we know that number of days taken by B complete the work is 'x/2', we substitute the 'x' value.
Hence the evaluation '12/2' where 12 is the value of 'x'.
HENCE THE TIME REQUIRED BY B TO COMPLETE THE WORK IS 6 DAYS.
(1)
Manish said:
8 years ago
One day work of a,b&c=1/2
let a's one-day work=x , then b's one day work 2x & c work 3x
x+2x+3x=1/2
6x=1/2
x=1/12
b's one day work=2*1/12
=1/6
Therefore total work in 6 days.
let a's one-day work=x , then b's one day work 2x & c work 3x
x+2x+3x=1/2
6x=1/2
x=1/12
b's one day work=2*1/12
=1/6
Therefore total work in 6 days.
(1)
Abhishek said:
5 years ago
Let's assume.
C takes 4 days to do X work.
B takes 6 days for the same X work.
A takes 12 days for the same X work.
so, efficiency
A = 1/12.
B = 1/6.
c = 1/4.
So, as they all together takes 2 days to work,
x/(1/12)+(1/6)+(1/4) = 2
From that, we got X ( total work ) = 1
So time taken alone by;
B = 1/(1/) = 6 days.
C takes 4 days to do X work.
B takes 6 days for the same X work.
A takes 12 days for the same X work.
so, efficiency
A = 1/12.
B = 1/6.
c = 1/4.
So, as they all together takes 2 days to work,
x/(1/12)+(1/6)+(1/4) = 2
From that, we got X ( total work ) = 1
So time taken alone by;
B = 1/(1/) = 6 days.
(1)
Rahul said:
9 months ago
@All.
Here is the explanation for the answer.
As per the question, A=2B, A=2C.
equating, we get B = 3C/2,
A+B+C = 1/2.
Substitute the derived relations in the above equation, and the answer will be somewhere around 6.333333.
So, the correct answer is 6 days.
Here is the explanation for the answer.
As per the question, A=2B, A=2C.
equating, we get B = 3C/2,
A+B+C = 1/2.
Substitute the derived relations in the above equation, and the answer will be somewhere around 6.333333.
So, the correct answer is 6 days.
(1)
G JOGI RAO said:
1 decade ago
Hi @Kiran.
If 6A = 2 then A = 3.
But you said it A = 12 give proper explanation?
If 6A = 2 then A = 3.
But you said it A = 12 give proper explanation?
Dipika said:
1 decade ago
If C takes x days to complete a work A will take 3x days.
If B takes y days to complete a work A will take 2y days.
But 3x = 2y, so x = 2/3y.
As per ques, 1/2y+y+2/3y = 1/2.
Therefore y = 6.
B takes 6 days to complete the work.
If B takes y days to complete a work A will take 2y days.
But 3x = 2y, so x = 2/3y.
As per ques, 1/2y+y+2/3y = 1/2.
Therefore y = 6.
B takes 6 days to complete the work.
Naseem Ahmad Saifi said:
1 decade ago
As per given:
2A = B => A = B/2......(1).
3A = C......(2).
=> 3*B/2 = C......(2) (from 1st A = B/2).
(A+B+C)'s do the work in 2 days.
So (A+B+C)'s 1 day work is = 1/2.
Put the value of A and C from 1st and 2nd.
= (B/2+B+3*B/2) 's 1 day work = 1/2.
=> 6B/2, 1 day work = 1/2.
=> B's 1 day work = 1/2*2/6 = 1/6.
So B complete work in 6 days.
2A = B => A = B/2......(1).
3A = C......(2).
=> 3*B/2 = C......(2) (from 1st A = B/2).
(A+B+C)'s do the work in 2 days.
So (A+B+C)'s 1 day work is = 1/2.
Put the value of A and C from 1st and 2nd.
= (B/2+B+3*B/2) 's 1 day work = 1/2.
=> 6B/2, 1 day work = 1/2.
=> B's 1 day work = 1/2*2/6 = 1/6.
So B complete work in 6 days.
Vidivelli said:
1 decade ago
Let us consider the time taken by B is 2x.
So the time taken by A is "twice of B" then A=4x.
Similarly if time taken by B is x/2, the time taken by A is (2*x/2) = x; the time taken by C is x/3.
So the time taken by A is thrice of C (3* x/3). Hence we get x+x/2+x/3.
Since we consider work for one day we take inverse 1/x+2/x+3/x = 1/2.
So the time taken by A is "twice of B" then A=4x.
Similarly if time taken by B is x/2, the time taken by A is (2*x/2) = x; the time taken by C is x/3.
So the time taken by A is thrice of C (3* x/3). Hence we get x+x/2+x/3.
Since we consider work for one day we take inverse 1/x+2/x+3/x = 1/2.
Punitsw said:
1 decade ago
In simple words:
A:B:C = 1:2:3 (Total 6 equivalent to A).
Now A, B and C together complete work in 2 days (i.e in 12 man days of A). So if A, B or C do the work alone, the required days would be:
A = 12 days.
B = 6 days.
C = 4 days.
A:B:C = 1:2:3 (Total 6 equivalent to A).
Now A, B and C together complete work in 2 days (i.e in 12 man days of A). So if A, B or C do the work alone, the required days would be:
A = 12 days.
B = 6 days.
C = 4 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers

