Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3

Then, 1 + 2 + 3 = 1
x x x 2

6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

Discussion:
68 comments Page 2 of 7.

Raj said:   9 years ago
2A = B.......eqn1.
3A = C.......eqn2.

A + B + C = 2days
A + 2A + C = 2days (from the eqn1),
A + 2A + 3A = 2days(from the run2),
6A = 2days ,
A = 2/6,
A = 1/3 days.

i.e A takes 3days to work.

We have B=2A.
B=2(3),
B=6.
That's B takes 6 days to complete.
(1)

Manish said:   8 years ago
One day work of a,b&c=1/2
let a's one-day work=x , then b's one day work 2x & c work 3x
x+2x+3x=1/2
6x=1/2
x=1/12
b's one day work=2*1/12
=1/6

Therefore total work in 6 days.
(1)

Aadhi said:   7 years ago
@Ajay.

How to find efficiency ratio?
(1)

Abhishek said:   5 years ago
Let's assume.
C takes 4 days to do X work.
B takes 6 days for the same X work.
A takes 12 days for the same X work.

so, efficiency
A = 1/12.
B = 1/6.
c = 1/4.

So, as they all together takes 2 days to work,

x/(1/12)+(1/6)+(1/4) = 2
From that, we got X ( total work ) = 1
So time taken alone by;
B = 1/(1/) = 6 days.
(1)

G JOGI RAO said:   1 decade ago
Hi @Kiran.

If 6A = 2 then A = 3.

But you said it A = 12 give proper explanation?

Vidivelli said:   1 decade ago
Let us consider the time taken by B is 2x.

So the time taken by A is "twice of B" then A=4x.

Similarly if time taken by B is x/2, the time taken by A is (2*x/2) = x; the time taken by C is x/3.

So the time taken by A is thrice of C (3* x/3). Hence we get x+x/2+x/3.

Since we consider work for one day we take inverse 1/x+2/x+3/x = 1/2.

Naseem Ahmad Saifi said:   10 years ago
As per given:

2A = B => A = B/2......(1).

3A = C......(2).

=> 3*B/2 = C......(2) (from 1st A = B/2).

(A+B+C)'s do the work in 2 days.

So (A+B+C)'s 1 day work is = 1/2.

Put the value of A and C from 1st and 2nd.

= (B/2+B+3*B/2) 's 1 day work = 1/2.

=> 6B/2, 1 day work = 1/2.

=> B's 1 day work = 1/2*2/6 = 1/6.

So B complete work in 6 days.

Punitsw said:   10 years ago
In simple words:

A:B:C = 1:2:3 (Total 6 equivalent to A).

Now A, B and C together complete work in 2 days (i.e in 12 man days of A). So if A, B or C do the work alone, the required days would be:

A = 12 days.
B = 6 days.
C = 4 days.

MONA said:   10 years ago
In simple way:

A =2B , A = 3C,So ratio will be = A : B : C = 1 : 2 : 3.
A = 1 unit/day
B = 2unit/day
C = 3unit/day

A + B + C = 6unit/day.

We don't know the total work in units.
So,
A + B + C = 2 Days
TOTAL WORK/DAYS = 6.
TOTAL WORK = 6 * 2 = 12 UNITS.

So,B = 12/2 = 6 Days.

Vandana said:   9 years ago
One query, please answer this question:

A, B and C together can finish a piece of work in 12 days, A and C together work twice as much as B, A and B together work thrice as much as C. In what time could each do it separately?


Post your comments here:

Your comments will be displayed after verification.