Marks : 2/20


Total number of questions
20
Number of answered questions
0
Number of unanswered questions
20
Test Review : View answers and explanation for this test.

1.
A systematic job improvement sequence will consist of
motion study
time study
job enrichment
all of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

2.
When slack of an activity is negative
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
all of the above
Your Answer: Option
(Not Answered)
Correct Answer: Option

3.
Military type of organisation is known as
line organisation
functional organisation
line and staff organisation
line, staff and functional organisation
Your Answer: Option
(Not Answered)
Correct Answer: Option

4.
Line organisation is suitable for a big organisation.
Correct
Incorrect
Your Answer: Option
(Not Answered)
Correct Answer: Option

5.
A-B-C analysis is used in
CPM
PERT
inventory control
all of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

6.
The product layout is more amenable to automation than process layout.
True
False
Your Answer: Option
(Not Answered)
Correct Answer: Option

7.
Which of the following statement is correct?
A-B-C analysis is based on Pareto's principle.
Simulation can be used for inventory control.
Economic order quantity formula ignores variations in demand pattern
all of the above
Your Answer: Option
(Not Answered)
Correct Answer: Option

8.
Standard time is equal to
normal time minus allowances
normal time plus allowances
representative time multiplied by rating factor
normal time taken by an operation
Your Answer: Option
(Not Answered)
Correct Answer: Option

9.
Micromotion study is
analysis of one stage of motion chart
motion study, when seen on a time chart
subdivision of an operation into therbligs and their analysis
enlarged view of motion study
Your Answer: Option
(Not Answered)
Correct Answer: Option

10.
Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is
25
50
75
100
Your Answer: Option
(Not Answered)
Correct Answer: Option

11.
Queuing theory is used for
job-shop scheduling
inventory problems
traffic congestion studies
all of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

12.
Slack represents the difference between the
earliest completion time and latest allowable time
latest allowable time and earliest completion time
earliest completion time and normal expected time
latest allowable time and normal allowable time
Your Answer: Option
(Not Answered)
Correct Answer: Option

13.
When slack of an activity is positive
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
Your Answer: Option
(Not Answered)
Correct Answer: Option

14.
In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost.
True
False
Your Answer: Option
(Not Answered)
Correct Answer: Option

15.
Time study is used to
determine standard costs
determine the number of machines a person may run
provide a basis for setting piece price or incentive wages
all of the above
Your Answer: Option
(Not Answered)
Correct Answer: Option

16.
Product layout is used for
job production
batch production
mass production
any one of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

17.
In jobbing production
highly skilled workers are needed
unit costs are high
operations are labour-intensive
all of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

18.
Halsey plan of wage incentive
is not applied to all level of workers
is applied to all level of workers
does not guarantee minimum wage
is based upon efficiency of worker
Your Answer: Option
(Not Answered)
Correct Answer: Option

19.
Which of the following networks is correctly drawn?
Your Answer: Option
(Not Answered)
Correct Answer: Option

20.
Linear programming can be applied successfully to
chemical industry
oil industry
banks
all of these
Your Answer: Option
(Not Answered)
Correct Answer: Option

*** END OF THE TEST ***