Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 35)
35.
Slack represents the difference between the
earliest completion time and latest allowable time
latest allowable time and earliest completion time
earliest completion time and normal expected time
latest allowable time and normal allowable time
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
9 comments Page 1 of 1.

Vinay said:   3 years ago
Answer is option B.

Harish said:   3 years ago
Option B should be the correct answer.

Uri gagrin said:   5 years ago
I think B is the right answer.

Maharshi Gandhi said:   5 years ago
The correct Answer is [B] Latest allowable time and earliest completion time.

Debashis Das said:   5 years ago
Option B is the right Answer.
(1)

Hardik tekwani said:   7 years ago
Slack = latest allowable time - earliest expected time.

Dayanand said:   7 years ago
Yes, answer B is the right answer.

Zahid said:   8 years ago
The answer is B not A.

Slack = Latest finish time-Earliest finish time.

= TL-TE.

K thakur said:   8 years ago
Answer is option B.

Slack = Latest finish time-Early finish time.

Post your comments here:

Your comments will be displayed after verification.