15.
In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 4 of 4.
Sonu said:
1 decade ago
What about option B which has 24+D1 days?
Kuldip said:
1 decade ago
Critical path is one which takes more time to complete. So 1-2-5-6-7-8-9 is taking 22 days and other path 21 day so 1256789 should be the critical path.