In a network shown in the below figure, the critical path is along
1-2-3-4-8-9
1-2-3-5-6-7-8-9
1-2-3-4-7-8-9
1-2-5-6-7-8-9
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 4 of 4.

Sonu said:   1 decade ago
What about option B which has 24+D1 days?

Kuldip said:   1 decade ago
Critical path is one which takes more time to complete. So 1-2-5-6-7-8-9 is taking 22 days and other path 21 day so 1256789 should be the critical path.