Discussion Forum : Industrial Engineering and Production Management - Section 3 (Q.No. 18)
18.
A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
Correct
Incorrect
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Prashant said:   6 years ago
Activity time is zero because it's an earliest starting time is equal to latest finish time. So it is dummy activity.

Dr.R.Saravanan said:   7 years ago
A dummy activity neither consumes resource and Time so [B] is the correct answer.