16.
Which of the following conditions are necessary for applying linear programming?
17.
Indirect expenses include
18.
A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
19.
In time study, normal time is more than the standard time.
20.
The start or completion of task is called