The essential condition for the decompression of an activity is that

[A]. the project time should change due to decompression
[B]. after decompression the time of an activity invariably exceeds its normal time
[C]. an activity could be decompressed to the maximum extent of its normal time
[D]. none of the above

Answer: Option C

Explanation:

No answer description available for this question.

Ram said: (Mar 13, 2015)  
What is decompression here? Please anyone say.

Pukhraj said: (Oct 29, 2018)  
Decompression refers to the crashing of an activity.

Abel said: (Nov 24, 2018)  
It is not clear for me what is an activity crashing mean?