Mechanical Engineering - Industrial Engineering and Production Management

Exercise : Industrial Engineering and Production Management - Section 2
21.
The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
product layout
process layout
fixed position layout
a combination of line and process layout
Answer: Option
Explanation:
No answer description is available. Let's discuss.

22.
Standard time is equal to
normal time minus allowances
normal time plus allowances
representative time multiplied by rating factor
normal time taken by an operation
Answer: Option
Explanation:
No answer description is available. Let's discuss.

23.
In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost.
True
False
Answer: Option
Explanation:
No answer description is available. Let's discuss.

24.
The essential condition for the decompression of an activity is that
the project time should change due to decompression
after decompression the time of an activity invariably exceeds its normal time
an activity could be decompressed to the maximum extent of its normal time
none of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.

25.
Time study is carried out
by finding all the significant informations regarding the job, work place and machine tool etc.
by breaking up each operation into small elements which are measurable with the help of the measuring device accurately
by observing and recording the time taken by the operator for an operation
all of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.