Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 38)
38.
Which of the following statement is correct?
When slack of an activity is zero, it falls only on critical path.
CPM technique is useful to minimise the direct and indirect expenses.
Critical path of a net work represents the minimum time required for completion of project.
all of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
5 comments Page 1 of 1.

Dharmendra Kumar said:   5 years ago
Minimum time should be typed as the maximum time.

Vipul kumar said:   7 years ago
Yes CRITICAL PATH takes longest time from start to finish but this longest time is the shortest time (for the project) in which the project completion can take place, so answer D is correct.

Gauri said:   8 years ago
The critical path takes max time then how it's D?

Hardik said:   8 years ago
The critical path requires maximum time to finish.

Ahmad said:   1 decade ago
Critical path takes longest time from start to finish.