Mechanical Engineering - Industrial Engineering and Production Management - Discussion

38. 

Which of the following statement is correct?

[A]. When slack of an activity is zero, it falls only on critical path.
[B]. CPM technique is useful to minimise the direct and indirect expenses.
[C]. Critical path of a net work represents the minimum time required for completion of project.
[D]. all of the above

Answer: Option D

Explanation:

No answer description available for this question.

Ahmad said: (Jan 8, 2015)  
Critical path takes longest time from start to finish.

Hardik said: (Aug 30, 2016)  
The critical path requires maximum time to finish.

Gauri said: (Sep 26, 2016)  
The critical path takes max time then how it's D?

Vipul Kumar said: (Oct 13, 2017)  
Yes CRITICAL PATH takes longest time from start to finish but this longest time is the shortest time (for the project) in which the project completion can take place, so answer D is correct.

Dharmendra Kumar said: (Dec 6, 2019)  
Minimum time should be typed as the maximum time.

Post your comments here:

Name *:

Email   : (optional)

» Your comments will be displayed only after manual approval.