Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 41)
41.
When slack of an activity is positive
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
23 comments Page 2 of 3.

Ganeswar said:   8 years ago
The Answer should be A because positive does not include zero. Hence extra resource is available and the project is ahead of schedule.

Gopal said:   8 years ago
A is the correct answer.

Himanshu said:   8 years ago
According to me, Option A is right.

Vaiovino said:   8 years ago
The Correct option is A.

Kuldip said:   8 years ago
According to me, A is the correct answer.

Vipul kumar said:   8 years ago
A is the correct answer.

A.Abhilash said:   8 years ago
Option A is the correct answer.

Tinku said:   8 years ago
Option A is correct.

Karthi said:   7 years ago
The slack of an activity is +ve = option A.
For -ve = option B.
For 0 = option C.

Nitesh said:   7 years ago
According to me, the right answer is A.