When slack of an activity is positive
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
23 comments Page 2 of 3.

Himanshu said:   7 years ago
According to me, Option A is right.

Gopal said:   7 years ago
A is the correct answer.

Ganeswar said:   7 years ago
The Answer should be A because positive does not include zero. Hence extra resource is available and the project is ahead of schedule.

Chotu said:   7 years ago
Answer A is correct.

Because positive slack never be behind the schedule or on the critical path.

Samod said:   7 years ago
I too think the Correct answer is option A.

Jainesh said:   8 years ago
Correct answer is (a). I too agree.

Manoj said:   8 years ago
I agree @Ashu.

Ashu panchal said:   8 years ago
The correct answer is option [A].

When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.

When slack of an activity is negative- it represents that a program falls behind schedule and additional resources are required to complete the project in time.

When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.

Bhavesh Shingala said:   8 years ago
The correct answer is - option [A].

Kamal Bansal said:   9 years ago
Slack or float is time by which any activity delay without delaying project completion.

Positive slack-----Ahead of schedule.

Negative slack------Behind the schedule.

Zero slack ---------On the schedule.