Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 5)
                   
                                       
                                5.
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
 
                                    Discussion:
5 comments Page 1 of 1.
                
                        Puneet Kumar said: 
                         
                        9 years ago
                
                1) Most Likely time: Most frequently occur if the activity were repeated many times.
2) Pessimistic Time: The shortest possible time to complete the activity if everything is going right.
3) Optimistic Time: The longest possible time to complete the activity if everything is going wrong.
Probabilistic time (Mean of the above three Times) is calculated by given formula.
                2) Pessimistic Time: The shortest possible time to complete the activity if everything is going right.
3) Optimistic Time: The longest possible time to complete the activity if everything is going wrong.
Probabilistic time (Mean of the above three Times) is calculated by given formula.
                     (1)
                
            
                        Fatemeh said: 
                         
                        10 years ago
                
                Why? Please.
                
                        Rohit said: 
                         
                        8 years ago
                
                Thanks @Puneet Kumar.
                
                        Bhaskar said: 
                         
                        8 years ago
                
                @Puneet:
Optimistic Time: The shortest possible time to complete the activity if everything is going right.
Pessimistic Time: The longest possible time to complete the activity if everything is going wrong.
                Optimistic Time: The shortest possible time to complete the activity if everything is going right.
Pessimistic Time: The longest possible time to complete the activity if everything is going wrong.
                        Sid said: 
                         
                        7 years ago
                
                I agree with you, Thanks @Bhaskar.